Q: 7
A client is pressed for time and wants to launch a product with three components as soon as possible
to gain market share. An agile lead proposes the following agile strategy to gain time: Three teams
will work on the design and development of each component. Once all three components are
finished, they will be tested and integrated.
Is this agile strategy appropriate?