View Mode
Q: 11
A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?
Options
Q: 12
While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time- consuming project was executed previously in the organization. Which of the following actions should the PM take?
Options
Q: 13
A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?
Options
Q: 14
SIMULATION During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation. INSTRUCTIONS Review the email with the latest updates sent by the project sponsor and respond in the following order: 1. Select the best tool for tracking the server migration progress. 2. Select the new critical path. 3. Select the correct number of engineers required for the server migration phase. If at any time you would like to bring back the initial state of the simulation, please click the Reset All button. Project+ PK0-005 question Select the Appropriate Tool: Project+ PK0-005 question Project+ PK0-005 question Project+ PK0-005 question Project+ PK0-005 question Project+ PK0-005 question Select the new critical path. Option A Project+ PK0-005 question Option B Project+ PK0-005 question Option C Project+ PK0-005 question Project+ PK0-005 question
Your Answer
Q: 15
A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?
Options
Q: 16
A company asks some vendors to provide a solution for its specific needs. Which of the following documents should the company provide?
Options
Q: 17
Which of the following is a typical characteristic of Scrum?
Options
Q: 18
Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?
Options
Q: 19
During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?
Options
Q: 20
During the project execution, the sponsor would like to have a visual representation indicating the progress of the project The project is being managed using agile methodologies Which of the following tools would best help the sponsor with the request?
Options
Question 11 of 20 · Page 2 / 2

Premium Access Includes

  • Quiz Simulator
  • Exam Mode
  • Progress Tracking
  • Question Saving
  • Flash Cards
  • Drag & Drops
  • 3 Months Access
  • PDF Downloads
Get Premium Access
Scroll to Top

FLASH OFFER

Days
Hours
Minutes
Seconds

avail 10% DISCOUNT on YOUR PURCHASE