SIMULATION During a gate review meeting, the deliverable was rejected by the customer. INSTRUCTIONS Review the dashboard. • Part 1: Drag and drop each task, placing them in the correct order based on the project change control process. • Part 2: Select the proper document(s) to be updated. If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

If the deliverable got rejected, you always define new requirements first then check the impact (schedule/cost/risk), then update and test before demo. Docs to update are Statement of work, Schedule, and Change log. Pretty sure that's right, unless requirements were unofficially changed before the meeting?
Which of the following represents the critical path of the project?