Q: 1
A program with objectives that impact a large segment of the population receives negative
commentary from organizations representing the public interest.
What action should the program manager take first?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 2
Stakeholders make ad-hoc requests on a routine basis. This causes duplication of reporting and
communication gaps that affect the program's performance.
To resolve this situation, which of the following must go through critical review and change?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 3
If a risk has a probability of 60 percent and an impact of -$57,000 what will the expected monetary
value of the risk event be?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 4
During the selection of source process, you assign certain points towards various categories to judge
the vendors. Which type of source selection process is it?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 5
What does RACI stand for?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 6
You are the program manager of the NHQ Program for your organization. Your program is nearing the
completion of one of its major phases and there are several resources that should be released at this
time. What program management plan will guide you to release of the program resources and
transfer the resources and benefits to operations within the organization?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 7
The program manager compiles a program performance report for review by the program
governance board. The performance report indicates that the scope, quality, and schedule objectives
have been met, but costs and resource utilization are higher than expected. The program can no
longer deliver the planned return-on- investment within an acceptable level and the intended
benefits have not yet been realized.
After further analysis of the performance indicators, the program manager should do which of the
following?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 8
Which of the following individual should respond to the risk with the preplanned risk response?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 9
A two-year program is coming to an end. Many of the initial governance board members have moved
from their current posts or left the company. Several new members have joined, but have a short
association with the program, which changes the board’s expectations and focus. During the final
phase gate review, some board members are uncertain of their roles and expectations in the process.
How should the program manager handle this situation?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 10
A program manager building the world’s largest cruise ship is resolving the conflict between the two
main sponsors who cannot agree on the number of food and beverage outlets to have onboard.
What should the program manager do?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Question 1 of 20 · Page 1 / 2