1. Project Management Institute. (2017). The Standard for Program Management – Fourth Edition. Section 6.4.4.2
Quantitative Program Risk Analysis
p. 103. The standard defines EMV as a statistical concept calculated by multiplying the value of each possible outcome by its probability of occurrence.
2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. Section 11.4.2.2
Decision Tree Analysis
p. 434. This section explains that EMV is a key concept in decision tree analysis and is calculated by multiplying the probability and impact of risks.
3. Hulett
D. T. (2009). Practical Schedule Risk Analysis. Project Management Institute. Chapter 3
"Risk Analysis Methods
" discusses the fundamentals of quantitative risk analysis
including the calculation of Expected Monetary Value (EMV) as a product of probability and impact.