1. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 5.5.3
Program Financial Framework
p. 78. "The to-complete performance index (TCPI) is a comparative EVM metric that is used to determine the feasibility of achieving the cost objective of a program component."
2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 7.4.2.2
Data Analysis
p. 265. "The to-complete performance index (TCPI) is a measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal
expressed as the ratio of the cost to finish the outstanding work to the remaining budget."
3. Project Management Institute. (2011). Practice Standard for Earned Value Management (2nd ed.). Section 4.6
To-Complete Performance Index (TCPI)
p. 23. "The TCPI is the calculated cost performance index that is achieved on the remaining work to meet a specified management goal
such as the BAC or the EAC."