Q: 11
Temporary shoring of a masonry wall should remain in place until what point?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 12
Refer to the exhibit.
Refer to the exhibit.
For which of the following connections could diagonal bracing be eliminated?
Refer to the exhibit.
For which of the following connections could diagonal bracing be eliminated?Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 13
In which of the following locations should wood building products be pressure treated when used in
a climate that promotes decay? Check the four that apply.
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 14
Given the information below, which of the following is the cost of 1,850 sq. ft. of brick veneer?
Cost of brick – $500 per 1,000 brick
Cost of masonry cement, sand, etc. – $160 per 1,000 brick
Cost of labor – $675 per 1,000 brick
680 bricks per 100 sq. ft.
5% waste of material
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 15
During plan review of an office building, the reviewer informs the architect of new regulations that
require storage rooms greater than 150 sf be 1-hour fire rated. The proposed design has three 200 sf
storage rooms that must meet the fire protection requirements. The architect needs to recommend
how to meet this requirement with minimal effect on cost, time, and program.
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 16
Refer to the exhibit.
Refer to the exhibit.
It is required to cut a hole in the web of the beam shown.
Which of the locations would be best? Check the two that apply.
Refer to the exhibit.
It is required to cut a hole in the web of the beam shown.
Which of the locations would be best? Check the two that apply.Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 17
An architect is designing a sub-surface drainage system that outfalls into a site retention pond. The
recommended shape, size, and slope of the drainage lines need to be determined for primarily which
of the following purposes?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 18
What is the most destructive factor affecting the durability of mortar joints?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 19
HOTSPOT
Refer to the exhibit.
Construction document drawings are in the final review stages. The architect needs to coordinate the
casework detail with the probable cost estimate.
Click on the drawing note in the casework section that does not align with the cost estimate.

Refer to the exhibit.
Construction document drawings are in the final review stages. The architect needs to coordinate the
casework detail with the probable cost estimate.
Click on the drawing note in the casework section that does not align with the cost estimate.

Your Answer
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 20
HOTSPOT During drawing review, a discrepancy is found between the drawings and room 101 on the finish schedule. Click in the cell on the room finish schedule that does not match the drawings. 
Your Answer
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Question 1 of 10