AXELOS. (2013). Portfolio
Programme and Project Offices (P3O). The Stationery Office.
Section 6.4.5
'Recycle Capability/Disband': This section explicitly lists key activities for this stage
including: "Feedback of lessons learned to the corporate knowledge base (e.g. a COE)". This directly supports option C as the correct answer.
Figure 6.3
'Lifecycle for a temporary P3O': This figure illustrates the final stage as 'Recycle Capability/Disband'
confirming the context of the question. The activities listed under this stage
such as redeployment of staff (related to option A) and handover of products (related to option D)
are part of the overall process
but feeding back lessons is central to "recycling capability".