1. AXELOS. (2013). Portfolio
Programme and Project Offices (P3O). The Stationery Office.
Section 3.4.3
Assurance and Gating
p. 29: "Assurance provides an independent assessment of the health of a project or programme
checking that the project or programme is still aligned with the corporate strategy and that the business case is still valid."
Appendix A
Glossary
p. 157: "Assurance - ...In P3O
assurance is independent of the team that is managing the work." This explicitly confirms that the assurance function must be separate from the delivery team.
Figure 3.5
P3O Functional Areas
p. 26: This figure visually separates 'Standards and Assurance' from 'Delivery Support'
reinforcing the distinction between the independent oversight role and the integrated support role.