The ABC company specializes in the development of wind turbine blades for use in large-scale
commercial wind energy production systems. The company has manufacturing facilities located in
Palm Springs, California, Omaha, Nebraska, and Winnipeg, Manitob
a. Each of these plants supplies a different manufacturer that builds and sells complete systems. The
turbine blades are custom engineered to meet each manufacturer's design specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics.
However, recent improvements in composite materials, coupled with enhanced automated methods
for precision application of materials during the molding process, have led to significant reduction in
weight, increase in strength, and greatly improved blade longevity. The company has pioneered the
development of a proprietary automated process for continuous extrusion of the turbine blades.
Patents have been filed to protect the process, but certain trade secrets must be closely guarded.
The company has a mature Enterprise Architecture organization that is supported by a cross-
functional Architecture Review Board. The Chief Information Officer and the Chief Operating Officer
co-sponsor the Enterprise Architecture program.
The company has used T0GAF and its Architecture Development Method (ADM) to develop its
automated manufacturing processes and systems that are used to design, manufacture, and test the
blade assemblies. They have adapted their Enterprise Architecture to closely follow the TOGAF 9
framework. All of the company's enterprise architects have been trained and certified on TOGAF 9.
Recently, an architecture project was completed that defined a standard approach for controlling the
Automated Test System that is used at each plant to perform final quality assurance tests on each
completed blade assembly. The Manufacturing Architecture Board approved the plan for immediate
implementation at each plant.
An Architecture Contract was developed that detailed the work needed to implement and deploy the
new Automated Test System controller. The Chief Engineer, sponsor of the activity, has expressed
concern that a uniform process be employed at each site to ensure consistency.
Refer to the Scenario
You are the Lead Architect for this activity.
You have been asked to recommend the best approach to adopt to address the Chief Engineer's
concern.
Based on TOGAF 9, which of the following is the best answer?