1. AXELOS. (2010). Management of Value (MoV). The Stationery Office (TSO).
Section 7.4.6, Develop proposals, Page 78: "The main output from this step is one or more Value Improving Proposals (VIPs)... Each VIP should be a self-contained document that provides decision-makers with sufficient information to make a decision on whether to proceed with the proposal."
Section 7.3.3, Plan the MoV study, Page 68: This section describes the creation of the MoV Study or Project Plan as a key output for managing the study.
Section 7.5.1, Implement proposals, Page 80: This section details the development of an implementation plan (or strategy) for the approved VIPs.
Chapter 9, How to embed MoV in an organization, Page 93: Discusses the MoV Policy as a tool for embedding MoV at an organizational level.