Q: 11
To determine the area of interior nonstructural elements, the LEED AP will include which one of the
following in the calculation for Materials and Resources Credit, Interiors Life Cycle Impact Reduction,
Option 1. Interior Reuse?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 12
A project owner is seeking Location & Transportation Credit, Surrounding Density and Diverse Uses
for an office that is being relocated. In order to promote walkability and reduce the distance driven
by employees, which of the following solutions should the project owner consider?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 13
In a goal-setting workshop, a decision is made to place circulation at the exterior of the office
perimeter next to the window wall. Which of the following is an example of integrated decision-
making?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 14
Best practices recommend that the LEED AP confirm that minimum program requirements have been
met
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 15
When attempting Regional Priority Credit, Regional Priority what must be provided in the
documentation?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 16
The project team for a bank project located in a mall is wondering whether they can earn Location
and Transportation Credit Surrounding Density and Diverse Uses, Option 2. Diverse Uses. When
evaluating a map of nearby diverse uses, which of the following would you recommend to be
entered in the calculation?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 17
Design is underway for a new tenant suite with 4,000 ft2 (371.6 m2) of net occupiable are
a. The project build-out will include all new HVAC systems. Operable windows are installed as
follows:
· A total 75 ft2 (7.0 m2) located within 15 ft. (4.6 m) of all spaces
. A total 50 ft2 (4.6 m2) located within 25 ft. (7.6 m) of all spaces
Which design and documentation strategies must be used to demonstrate compliance with Indoor
Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 18
For Energy and Atmosphere Prerequisite, Fundamental Commissioning (Cx) and Verification, the final
Cx report must include the
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 19
A Client is fitting out a building with area 20,500 ft2 (1 904.5 m2) and wishes to pursue the Energy
and Atmosphere Credit, Enhanced Commissioning. Who may be appointed as the Commissioning
Authority (CxA) for the project?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 20
In the pre-design phase, a plumbing engineer identified that the low-flow fixtures which met the
Owner's requirements could achieve total reductions in indoor water usage of 39%. Which strategies
should be assessed to meet the Owner's Project Requirements goals of 45% reduction?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Question 11 of 20 · Page 2 / 2