Q: 20
In the pre-design phase, a plumbing engineer identified that the low-flow fixtures which met the
Owner's requirements could achieve total reductions in indoor water usage of 39%. Which strategies
should be assessed to meet the Owner's Project Requirements goals of 45% reduction?
Options
Discussion