Q: 17
Design is underway for a new tenant suite with 4,000 ft2 (371.6 m2) of net occupiable are
a. The project build-out will include all new HVAC systems. Operable windows are installed as
follows:
· A total 75 ft2 (7.0 m2) located within 15 ft. (4.6 m) of all spaces
. A total 50 ft2 (4.6 m2) located within 25 ft. (7.6 m) of all spaces
Which design and documentation strategies must be used to demonstrate compliance with Indoor
Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance?