Q: 1
A supplier of software has received a request to quote for a product. The software supplier considers
that the buying organisation making the request provides relatively little benefit or alignment to
their own strategy. Which one of the following options describes how the supplier might react to the
buyer?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 2
Which of the following are most likely to negatively affect the suppliers’ bargaining power in a
specific market? Select TWO that apply:
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 3
A company is planning the procurement of an IT system and wants to agree a through-life contract
with the supplier to ensure ongoing system support. The first step in producing that specification
should be to:
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 4
When should procurement professional tolerate a risk?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 5
Which of the following content should a performance specification feature? Select TWO that apply.
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 6
Royal Navy is preparing a through-life contract. They put to the contract a term on rectification of
operational defects and planning and delivery of Fleet Time Support Periods. Which part of through-
life requirement does this term belong to?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 7
XYZ Ltd is producing an engine which consists of many components. The procurement manager
wants to find cost reduction opportunities and minimise part varieties. Which of the following may
help her to achieve these objectives?
1. Value analysis
2. Segment analysis
3. Variety reduction
4. Standardisation
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 8
Aldar Properties is a property developer in UAE. In last month, it spent $2,160 for 10 tons of steel. In
this month, it had planned 10% increment in budget for steel comparing to last month. But the
number of orders boosted and total spend on steel reached $1,992.1 while Aldar has imported 11
tons. What is the main cost driver of steel budget?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 9
Which of the following is the new technology that has impact on manufacturing sector?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 10
Which of the following are 'secondary sources' of data for costs and prices?
Industry press
Published economic indices
Trade fairs
Buyer's database on market data
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 11
Sealines Inc is developing its fleet of cargo ships. The company is planning to build a new ship
powered by natural gas. Brian, the procurement manager at Sealines, suggests the project team to
develop a through-life specification before engaging with the supplier. Is this a correct approach?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 12
Which of the following statements describes a correct example of an indirect cost?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 13
Which of the following technology is likely to be an innovation in financial sector?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 14
To strengthen its market presence, ABC Group decided to develop a new product. A cross-functional
team was formed to discuss the scope and the functions of the product. They will also survey the
potential customers to see what they like, what they love, and what they dislike. What is this process
called?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 15
A drawing is an example of…?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 16
Which of these are variable costs?
Staff overtime
Premises costs
Insurance costs
Material costs
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 17
Halfords is a major bicycle and car parts retailer with long history in the market. Its suppliers are
plentiful and there is no threat of forward integration. Some other smaller retailers are applying 3D-
printing technology to make personalized bicycle parts but their market share is relatively low. 3D-
printing technology is an example of which competitive force?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 18
In Kano model, which of the following types of requirement should be excluded from the product or
service?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 19
Sabic is a petrochemical manufacturer. It wants to digitalise its operation and is looking for new IT
system. The procurement manager approaches this matter with a through-life specification. He
supposes that stating “good quality” in the specification will be enough for quality standard section.
Is the procurement manager’s thought appropriate?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 20
Which of the following are typical social considerations throughout the contract life cycle? Select the
TWO that apply.
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.