Q: 7
XYZ Ltd is producing an engine which consists of many components. The procurement manager
wants to find cost reduction opportunities and minimise part varieties. Which of the following may
help her to achieve these objectives?
1. Value analysis
2. Segment analysis
3. Variety reduction
4. Standardisation
Options