Q: 19
DRAG DROP
An organisation is looking for management system initial certification. Please identify the sequence
of the activities to be undertaken by the organisation.
To complete the sequence click on the blank section you want to complete so that it is highlighted in
red, and then click on the applicable text from the options below. Alternatively, you may drag and
drop the options to the appropriate blank section.


Your Answer
Discussion
Establish system, plan audits, do internal audit, management review, hire cert body, finish corrective actions. Pretty sure that's right?
Establish management system → plan audit programme → internal audits → management review → certification body (stage 1 & 2) → corrective actions. This matches the standard ISMS certification flow per PECB. Pretty sure that's correct, but open to tweaks if someone spots an exception here.
Not sure but I'd put corrective actions right after internal audits, then management review, then engage certification body. Anyone see a flaw?
Plan audit programme, conduct internal audits, engage certification body, management review, corrective actions, establish management system. I think this is the order but not totally sure since management review can sometimes come earlier. The trap here is mixing up certification body and management review.