Q: 3
The product owner has found the overall goals of an initiative need to change and discusses the
revisions with the team. The estimate of the revised work is greater than the original, which will
likely cause the team to miss the fixed release date. The team works actively together to understand
the new information about what is valuable and what is not, and find ways to eliminate work that
does not directly relate to the newly expressed value. The team is demonstrating which agile value?