Q: 11
What provision should a designer include in the contract to minimize liability in claims that arise from delays caused by other project members?
Options
Q: 12
A designer is planning an office remodel where the tenant is relocating their existing microwaves. After project completion, the tenant is disappointed to discover the outlets for the microwaves were installed at the incorrect height. What could the designer have done to prevent this?
Options
Q: 13
Changes made to the contract documents during the bid (tender) process are documented in a(n)
Options
Q: 14
In a soft goods furniture specification, what information should always be included?
Options
Q: 15
The purpose of a post-occupancy evaluation is to determine
Options
Q: 16
Which of the following installations would require a structural engineer to be involved?
Options
Q: 17
A designer is working on a joint venture project with a local engineering firm for a large university project. What drawing system will BEST incorporate coordination of project information?
Options
Q: 18
What should be addressed FIRST in a letter of agreement?
Options
Q: 19
In new construction, when would be the appropriate time to schedule an on-site review of wall blocking for an artwork package?
Options
Q: 20
During construction, a designer has been informed that the floor tile specified will delay occupancy. What is the BEST course of action?
Options
Question 11 of 20 · Page 2 / 2

Premium Access Includes

  • Quiz Simulator
  • Exam Mode
  • Progress Tracking
  • Question Saving
  • Flash Cards
  • Drag & Drops
  • 3 Months Access
  • PDF Downloads
Get Premium Access
Scroll to Top

FLASH OFFER

Days
Hours
Minutes
Seconds

avail 10% DISCOUNT on YOUR PURCHASE