1. Piotrowski
C. M. (2017). Professional Practice for Interior Designers (6th ed.). Wiley.
Page 437
Chapter 18
"Contract Administration: Construction and Order Installation": The text emphasizes that substitutions must be formally requested and approved. "The designer must review the proposed substitution for compliance with the specifications... If the designer agrees that the substitution is acceptable
he or she then consults the client for final approval." This directly supports the need for client agreement (Option B) and refutes making a unilateral change (Option A).
2. American Institute of Architects. (2017). AIA Document A201–2017
General Conditions of the Contract for Construction.
Article 7
"Changes in the Work
" Section 7.2
"Change Orders": A Change Order is defined as an instrument prepared by the Architect/Designer and signed by the Owner
Contractor
and Architect/Designer
stating their agreement upon a change in the Work. This establishes the legal and procedural requirement for owner (client) approval for any modification
including a material substitution.
3. Ballast
D. K. (2018). The Interior Design Reference Manual (6th ed.). Professional Publications
Inc.
Chapter 46
"Contract Administration
" Section on "Substitutions": This section outlines the standard procedure where a designer evaluates a proposed substitution but must present it to the owner for final approval. It states
"If the substitution is acceptable
the designer notifies the contractor and issues a change order if the cost or time of construction is affected." This process underscores that client approval is a mandatory step before any change is finalized.