View Mode
Q: 9
Which of the following are Test Closure activities? a All results lodged in configuration management system - for example test plans, results, logs, reports. b. Plans in place for lessons to be learnt to ensure that good practices are repeated and poor practices are not. c. Checks undertaken to ensure that all test work is completed - all tests executed or skipped, all defects managed to appropriate conclusion. d. All project closure activities completed - for example customer training completed, and analysis of vendor performance undertaken. e. AM testing work products delivered to those that need them - for example environments/ regression test sets passed to maintenance. f. Checks undertaken to ensure that all tests have been executed, with all defects confirmed as fixed by retesting. SELECT ONE OPTION
Options
Question 9 of 30

Premium Access Includes

  • Quiz Simulator
  • Exam Mode
  • Progress Tracking
  • Question Saving
  • Flash Cards
  • Drag & Drops
  • 3 Months Access
  • PDF Downloads
Get Premium Access
Scroll to Top

FLASH OFFER

Days
Hours
Minutes
Seconds

avail 10% DISCOUNT on YOUR PURCHASE