Q: 13
After collecting the control information on a light rail project within an original budget of 200.000
work hours, the construction contractor is ready for their monthly progress meeting with the client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and
110.000 work hours paid. The stated progress by the contractor Is 60%.
What is a method for figuring estimate at completion (EAC)?
Options