Q: 12
After collecting the control information on a light rail project within an original budget of 200.0OO
work hours, the construction contractor is ready for their monthly progress meeting with the client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and
110.000 work hours paid. The stated progress by the contractor is 60%.
After collecting the control information on a light rail project within an original budget of
200.000work hours, the construction contractor is ready for their monthly progress meeting with the
client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and
110.000 work hours paid. The stated progress by the contractor Is 60%.
Is the percent complete stated by the contractor correct?