Q: 12
A Data Manager is drafting a report for clinical operations staff for support in responding to questions
about milestone-based site payments. Which is the most important information to display?
Options
Discussion
C vs A, but I think C is stronger since it shows both expected and actual milestones by site, which helps answer if a site is behind or on track for payments. More useful for justifying decisions to ops teams. Agree?
Probably A. Shows progress over time for each site, which seems useful for milestone payments support.