The Definition of "Done" ensures quality and clarity. The Scrum Guide states: "The Definition of Done
is a formal description of the state of the Increment when it meets the quality measures required for
the product."
A: It ensures the Increment is usable/releasable: "In order to provide value, the Increment must be
usable."
B: It provides transparency by setting a shared standard: "The Definition of Done creates
transparency by providing everyone a shared understanding of what work was completed."
C: The Sprint Goal is separate, defined in Sprint Planning.
D: Unit testing is a practice, not a purpose of "Done."
Exact Extract from Scrum Guide: "The Definition of Done creates transparency by providing everyone
a shared understanding of what work was completed as part of the Increment... In order to provide
value, the Increment must be usable." (Section: "Definition of Done")
Thus, A and B are correct.
Reference: Scrum Guide (2020), Section: "Definition of Done."