Scrum imposes no formal pre-conditions for Sprint Planning beyond the Sprint starting. The Scrum
Guide states: "Sprint Planning initiates the Sprint by laying out the work to be performed for the
Sprint."
A: A fully refined backlog isn’t required; refinement is ongoing.
B: Budget approval isn’t a Scrum concept.
C, D: The Sprint Goal is defined during, not before, Sprint Planning.
E: Some "Ready" items help, but it’s not mandatory; planning can refine items.
F: Correct—no pre-conditions exist; the team works with what’s available.
Exact Extract from Scrum Guide: "Sprint Planning is timeboxed to a maximum of eight hours for a
one-month Sprint... The Scrum Team may also invite other people to attend Sprint Planning to
provide advice." (Section: "Sprint Planning") No pre-conditions are listed.
Thus, F is correct.
Reference: Scrum Guide (2020), Section: "Sprint Planning."