1. SAP S/4HANA Help Portal
"Discontinuation of Materials": "During the MRP run
the system checks whether a material is to be discontinued. [...] If the discontinuation date is in the past
the system checks whether there is still stock of the material to be discontinued [...] If there is no more stock
the system reassigns the dependent requirements to the follow-up material." (This documentation directly links the discontinuation check to the MRP run).
2. SAP S/4HANA Help Portal
"MRP Logic
Discontinuation": "The discontinuation function is part of the MRP. It allows you to replace one material with another at a specific date." (This explicitly states that discontinuation is a function within MRP).
3. Official SAP Learning Courseware TS422 (SAP S/4HANA Production Planning and Manufacturing): Unit 5
Lesson on "Material Requirements Planning
" Section on "Discontinuation Control." The course material explains that the MRP planning run is the process that evaluates the discontinuation indicator
date
and follow-up material to redirect dependent requirements.