1. SAP S/4HANA Help Portal
"Scheduling for External Procurement": "In basic date scheduling
the system uses the planned delivery time from the material master record or purchasing info record and the goods receipt processing time from the material master record." (This supports option A).
2. SAP S/4HANA Help Portal
"Scheduling for In-House Production": "In basic date scheduling
the system always calculates the basic dates using the in-house production time that has been entered in the material master record." (This supports option D).
3. SAP S/4HANA Help Portal
"Basic Date Scheduling vs. Lead Time Scheduling": This document distinguishes the two methods
clarifying that basic date scheduling uses times from the material master (in-house production time
planned delivery time)
while lead time scheduling uses detailed data from the routing (like operation durations). (This supports the exclusion of option C).