You want to exchange data between SAP Project System and Microsoft What interface do you use?
Options
Q: 2
Which statement is valid regarding networks?
Options
Q: 3
You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation., and have entered the quotation ... What is the typical sequence for the following business transactions and document.
Options
Q: 4
Resources How are capacity requirements determined?
Options
Q: 5
Dates How are earliest dates and latest dates of activities schedule?
Options
Q: 6
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.
Options
Q: 7
What are some of the possible functions in user status profiles? Note: There are 2 correct answers to this question.
Options
Q: 8
Cost and budget A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do not want to produce.. Which setup do you recommend?
Options
Q: 9
The__________________that you specify when you create a project definition is unique for the entire project. Choose the
Your Answer
Q: 10
Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question
Options
Question 1 of 20 Β· Page 1 / 2

Premium Access Includes

  • βœ“ Quiz Simulator
  • βœ“ Exam Mode
  • βœ“ Progress Tracking
  • βœ“ Question Saving
  • βœ“ Flash Cards
  • βœ“ Drag & Drops
  • βœ“ 3 Months Access
  • βœ“ PDF Downloads
Get Premium Access
Scroll to Top

FLASH OFFER

Days
Hours
Minutes
Seconds

avail 10% DISCOUNT on YOUR PURCHASE