1. SAP S/4HANA Documentation - Help Portal:
Document: Project System (PS) -> Structures -> Network -> Network Activity -> Control Key
Reference: The documentation explicitly lists the functions governed by the control key. One of the key indicators is "Cap. reqmts" (Capacity requirements). It states, "This indicator specifies that capacity requirements records are generated for the activity." This confirms the control key's role as the primary determinant.
2. SAP S/4HANA Documentation - Help Portal:
Document: Project System (PS) -> Dates -> Scheduling -> Capacity Planning in the Project System -> Determining Capacity Requirements
Reference: This section details the prerequisites for determining capacity requirements. It lists: "The control key for the activity must specify that capacity requirements are to be generated," alongside the need for a work center with formulas and the entry of work in the activity. This highlights the control key's mandatory role.
3. SAP Training Courseware (Implicit Content Structure):
Course: TS410 (Integrated Business Processes in SAP S/4HANA) & CTS412 (SAP S/4HANA Project Systems)
Reference: In the unit covering Project Structures and Networks, the control key is introduced as a central controlling instrument for activities. The configuration of the control key is shown to manage costing, scheduling, confirmations, and capacity planning, reinforcing its function as the master switch for these processes.