1. SAP S/4HANA Help Portal
"Service Activity": "You use service activities to procure external services... When the services have been performed
you enter them in a service entry sheet... When you accept the services that have been entered
the system posts the actual costs to the network activity."
Source: SAP SE. (2023). SAP S/4HANA - Product Assistance - Project System (PS) - Service Activity.
2. SAP S/4HANA Help Portal
"Externally-Processed Activity": "The system creates a purchase requisition for the activity... The purchasing department uses the purchase requisition to create a purchase order... Costs for an externally-processed activity are posted to the activity when the goods receipt for the purchase order is entered." (Note: For services
the "goods receipt" is the acceptance of the service entry sheet).
Source: SAP SE. (2023). SAP S/4HANA - Product Assistance - Project System (PS) - Externally-Processed Activity.
3. SAP S/4HANA Help Portal
"Actual Costs in the Project System": This document outlines the various ways actual costs can be posted to a project. It clearly distinguishes between internal activity allocation
confirmations
and postings from external procurement (goods receipts and invoice receipts)
reinforcing that external services are posted via the MM procurement process.
Source: SAP SE. (2023). SAP S/4HANA - Product Assistance - Project System (PS) - Actual Costs in the Project System.