1. SAP Help Portal for SAP S/4HANA
"Work Breakdown Structure (WBS)": This document states that the WBS is "the basis for planning costs
revenues
and payments
as well as for budgeting" (confirms D) and "the basis for organization and coordination in the project." The master data for a WBS element includes fields for organizational assignment like "Person Responsible" (confirms E).
2. SAP Help Portal for SAP S/4HANA
"Project Information System (PS-IS)": This section describes how the information system uses the project structure (WBS) to "summarize and aggregate data at any level" for analysis and reporting (confirms A).
3. SAP Help Portal for SAP S/4HANA
"Project Budgeting": This documentation details the process of assigning budgets to WBS elements. It states
"You can assign a budget to a project in the WBS." (confirms D).
4. SAP Help Portal for SAP S/4HANA
"Warehouse Task": This documentation for Extended Warehouse Management (EWM) explains that warehouse tasks are the basis for executing physical goods movements in the warehouse
managed by EWM objects
not the WBS (refutes B).