Q: 2
In the SAP Activate prepare phase, the cloud project is set up and officially launched. Which change
management activities are usually started in this phase? Note: There are 3 correct answers to this
question.
Options
Discussion
B seems like a fit since change impact analysis feels like a core activity you’d want to start as soon as possible. I don’t see why it couldn’t kick off in Prepare. Maybe not 100 percent sure, E could also work.
Yeah, it's A C D here.
A or C or D, pretty sure from SAP Activate guides and the official SAP Learning Hub resources.
Its A, C, D for Prepare. Stakeholder analysis, initial change plan, and aligning the change network strategy are all activities you'd start right away when launching the cloud project. Detailed impact analysis (B) and role mapping (E) belong to Explore phase, not here. Pretty sure about this from similar exam practice questions but let me know if I missed a nuance.
A C, D imo. Official SAP guides say stakeholder analysis, initial change planning, and setting up the change network are all part of Prepare. Change impact (B) and role mapping (E) come later in Explore. Pretty sure but happy to hear otherwise.
A C and D look right to me. Key stakeholder analysis and initial change planning always start early in Prepare, plus you set up the change network here too. B is more Explore phase, E's also usually a bit later. Open for debate if anyone disagrees.
A C, D tbh. These are all about planning and setting up change readiness which is Prepare phase work. B and E usually happen later once the project scope gets clearer. Open to pushback if I missed something.
A, C, D tbh. Had something like this in a mock and these matched what kicks off in Prepare phase.
Its A, C and D. B's a trap since detailed impact analysis is Explore phase, not Prepare.
C/D? The detailed impact stuff (B) should happen early.