1. SAP Help Portal
SAP S/4HANA Cloud
"Target Cost Calculation": "The target costs are calculated for the control quantity. In Product Cost by Order
the control quantity is the yield confirmed for the order at the time of variance calculation." The yield is the quantity posted during goods receipt. (Document section: Controlling > Product Cost Controlling > Cost Object Controlling > Product Cost by Order > Period-End Closing > Variance Calculation > Target Cost Calculation).
2. SAP S/4HANA Management Accounting II (S4F22) Course Material: In the unit covering Period-End Closing for Product Cost by Order
the process of variance calculation is detailed. It specifies that target costs are determined by valuating the quantity delivered to inventory (the goods receipt quantity) with the standard cost estimate. (Reference: S4F22
Unit on Period-End Closing
Lesson on Variance Calculation).