1. SAP Help Portal
SAP S/4HANA Cloud 2402
"Work in Process for Production Orders - Event-Based (3F0)": This document explains the process for event-based WIP calculation
which is controlled by the Results Analysis Key assigned to the production order. It states
"The calculation of work in process is based on a results analysis key."
2. SAP Help Portal
SAP S/4HANA Cloud 2402
"Variance Calculation (1BO)": This scope item documentation details the variance calculation process. It specifies
"The system calculates the variances by cost element for the production order... The variance key in the production order determines whether the variance is calculated."
3. SAP Help Portal
SAP S/4HANA Cloud 2402
"Overhead Costing - Actual (BEI)": This document describes how overhead is calculated. It clarifies that overhead is applied using a costing sheet
which is assigned to the production order. The Overhead Key is a component of the costing sheet's definition
not a direct field on the order itself. The document states
"The system finds the costing sheet through the valuation variant
which is specified in the production order."