Q: 3
When does the Scrum team receive formal confirmation that the user stories are completed to the
satisfaction of the product owner?
Options
Discussion
I always thought D made more sense here since the acceptance test is pretty direct. D
Probably A. The formal approval from the product owner is part of the sprint review, not during backlog review or retrospective.
Yeah it's during the sprint review, that's when the PO gives that formal thumbs up. A
Yeah I've always seen the PO give their official approval during the sprint review, not in retros or backlog reviews. A
A , the sprint review is where the Product Owner officially signs off on completed user stories. The other options don't really have that formal confirmation step built in. Pretty confident but open to correction if I'm missing something.
A tbh, that's always when the PO gives the official signoff in Scrum.
If the question said "first" instead of formal, would that make D a better pick since that's more direct testing?