Q: 13
In SAP Cloud ALM, which activity needs to be performed in the prepare phase?
Options
Discussion
A tbh, setting up the project is what happens first in the prepare phase. The trap here is C, but importing best practices comes a bit after kickoff. Open to other takes but that's how I've seen it.
Its A. Project setup always kicks off the prepare phase, not stuff like breaking down requirements yet.
Probably A, since the prepare phase is all about getting the basics in place like project setup before any detailed work starts. Stuff like orchestrating tests or user stories comes later on. Pretty sure on this one, but open to corrections.