Question 6 Q: 6 Which statement describes Release Planning? Options A: After looking at all the stories in the backlog, the team estimates their effort in detail. B: The team meets with the customer to negotiate the scope, cost and time of the release. C: The team and the Product Owner agree on an initial plan for the delivery of features. Save Question Show Answer Discussion 0 Clear Discussion Most voted Newest No comments yet. Be the first to comment. Post Be respectful. No spam. Correct Answer: C