Question 1 Q: 1 In developing a network the first task after listing the activities is to... Options A: Define activity durations B: Determine float C: Determine the interdependencies of activities D: Harmonise the activity to a calendar Save Question Show Answer Discussion 0 Clear Discussion Most voted Newest No comments yet. Be the first to comment. Post Be respectful. No spam. Correct Answer: C
Question 2 Q: 2 Which of the following statements refers to how scope is managed in a linear project but not an iterative project? Options A: Teams can act on new knowledge to change the scope. B: Teams can re-prioritise requirements within the scope. C: The scope of work is the starting point for the implementation of change control. D: Scope definition is assumed to be fixed for the whole project Save Question Show Answer Discussion 0 Clear Discussion Most voted Newest No comments yet. Be the first to comment. Post Be respectful. No spam. Correct Answer: D
Question 3 Q: 3 A Responsibility Assignment Matrix (RAM) can be used to: Options A: define the terms of reference of the project manager. B: define the limits of the project sponsor's responsibilities. C: allocate risk management response activities to project personnel. D: allocate work packages to those responsible for project work. Save Question Show Answer Discussion 0 Clear Discussion Most voted Newest No comments yet. Be the first to comment. Post Be respectful. No spam. Correct Answer: D
Question 4 Q: 4 What would be the most direct symptom of poor quality in the project? Options A: The project not using compliant management processes. B: The customer refusing to take delivery of the finished product. C: The failure of a quality assurance audit. D: The project finishing over budget. Save Question Show Answer Discussion 0 Clear Discussion Most voted Newest No comments yet. Be the first to comment. Post Be respectful. No spam. Correct Answer: B
Question 5 Q: 5 Which of the following actions would not help a team leader influence the performance of their team? Options A: Creating an exclusive environment. B: Providing clear roles and responsibilities. C: Promoting openness and honesty. D: Developing a trusting relationship. Save Question Show Answer Discussion 0 Clear Discussion Most voted Newest No comments yet. Be the first to comment. Post Be respectful. No spam. Correct Answer: A
Question 6 Q: 6 Which of these is a correct definition of an Estimate? Options A: The use of a range of tools and techniques to produce forecasts of the probable time or cost of completing work B: An educated guess that improves over time C: A forecast of the probable time or cost of completing work D: An estimate is an approximation of project time and cost targets that forms the basis of the contract Save Question Show Answer Discussion 0 Clear Discussion Most voted Newest No comments yet. Be the first to comment. Post Be respectful. No spam. Correct Answer: C
Question 7 Q: 7 Which project management process is NOT likely to be used when resolving an issue? Options A: Risk management B: Change control C: Scope management D: Team building Save Question Show Answer Discussion 0 Clear Discussion Most voted Newest No comments yet. Be the first to comment. Post Be respectful. No spam. Correct Answer: D
Question 8 Q: 8 Which of the following is a difference between deployment baselines in linear life cycles and iterative life cycles? Options A: Linear project life cycles set the deployment baseline for the whole project. B: In an iterative project life cycle the scope and quality are fixed in the deployment baseline. C: Only deployment baselines in iterative life cycles have an integrated baseline review. D: Only deployment baselines in linear life cycles have an integrated baseline review Save Question Show Answer Discussion 0 Clear Discussion Most voted Newest No comments yet. Be the first to comment. Post Be respectful. No spam. Correct Answer: A
Question 9 Q: 9 Which one of the following statements is true? Options A: Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget. B: Quality assurance provides confidence to stakeholders that requirements for quality will be exceeded. C: Quality control verifies that the project deliverables conform to specification, are fit for purpose and meet stakeholder expectations. D: Quality planning enables the project manager to manage the trade-off between customer expectations and budget. Save Question Show Answer Discussion 0 Clear Discussion Most voted Newest No comments yet. Be the first to comment. Post Be respectful. No spam. Correct Answer: C
Question 10 Q: 10 One disadvantage of physical communication is: Options A: its significant environmental impact when compared to other forms of communication. B: that no audit trail is available for review at a later date by project team members. C: it is reliant on technology being available to all relevant members of the project. D: that your body language may not reflect what you're saying when passing on information Save Question Show Answer Discussion 0 Clear Discussion Most voted Newest No comments yet. Be the first to comment. Post Be respectful. No spam. Correct Answer: A