HOTSPOT Column 1 is a list of individuals from within the Xan Insurance Company and their key responsibility within the Web project. For each individual in Column 1, select from Column 2 the Agile Project Management team role they are fulfilling. Each selection from Column 2 can be used once, more than once or not at all. Column 1 Manager of Web & Digital Media - will oversee and report progress on the delivery of the overall system. Finance Director - has budgetary control and will release finance for the project subject to expected benefits. Sales Manager - will formulate design options for new business processes that do not adversely affect business as usual. Operations Manager - oversees the design and integrity of the technical aspects of the solution. Column 2 Business Sponsor Business Analyst Business Ambassador Business Advisor Solution Developer Technical Coordinator DSDM Coach Project Manager
Q: 18
Your Answer
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Question 18 of 25