Comprehensive and Detailed Step-by-Step Explanation:
The High-level timing considerations heading requires statements that emphasize critical timelines,
milestones, or deadlines that need to be factored into the change strategy. Here's why D is the most
appropriate choice:
1. Understanding High-Level Timing Considerations:
Timing considerations refer to key deadlines, schedules, or milestones that impact the execution of
the change strategy.
This heading includes initiatives or actions that have a defined timeframe and are crucial for
achieving the strategic goals.
2. Option Analysis:
Option A: The traditional market has changed over the last year and UniCo can no longer rest on its
previous success.
This statement highlights a market condition but does not specify any timeline, milestone, or timing-
related requirement. It is more about market trends than timing considerations.
Eliminate.
Option B: UniCo lost significant market share in the last six months and faces ongoing increased
competition in the next year.
This statement discusses recent performance and anticipated competition, but it lacks a clear
timeline or milestone for action. It is focused on market dynamics, not timing.
Eliminate.
Option C: UniCo’s new finance system was delivered in the last quarter and training in the new
system is almost complete.
While this mentions past timing, it does not align with the heading as it focuses on completed tasks
rather than future timing or milestones.
Eliminate.
Option D: Completing the large contract with a Utilities company over the next nine months is a vital
step to achieving the end vision.
This statement provides a clear timeline ("next nine months") and links it to a critical milestone
(completing the contract) that contributes directly to UniCo's strategic goals.
Correct Answer.
3. Relevance in UniCo’s Scenario:
UniCo’s focus on repositioning itself in the market and delivering innovative solutions makes the
Utilities contract a pivotal milestone. The nine-month timeline directly impacts UniCo’s ability to
meet its strategic objectives and prove its capability in the new market segment.
4. Agile Practitioner Documentation Reference:
Milestone Planning in Agile: Agile emphasizes prioritizing and delivering on critical milestones within
time-boxed iterations.
Strategic Alignment: High-level timing considerations in change strategies align with Agile principles
by ensuring key initiatives are completed within the required timeframe to achieve overarching
goals.