Q: 1
Two team members are assigned to a task that is expected to start this Tuesday based on the
predecessor and the task constraint, but the Planned Start Date is showing as this Friday.
Why may this be the case?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 2
A company has decided that all projects for the year need to be created from templates and staffed
in the following quarter. The projects will need to remain in a backlog until the team has capacity to
work on them. There has been confusion previously because the team used Planning status for all
work not started.
What should the project manager do to help the team see the difference between work in the
backlog versus work that is now being planned?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 3
Which date type should an assignee update to change the completion date of a task?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 4
How is the primary assignee of a task determined?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 5
A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done
in 3 days.
What task setting needs to change to allow 4 users to complete this in less than 3 days?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 6
What are two ways to associate milestone steps to tasks? (Choose two.)
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 7
The marketing team should begin working on a task on September 23, complete it within 2 weeks
and take approximately 10 hours over that time span to execute the deliverable.
Which task settings need to be configured to meet these requirements?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 8
What parent object can have child objects?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 9
Which project status defaults the project condition to On Target?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Question 1 of 20 · Page 1 / 2