Q: 2
A company has decided that all projects for the year need to be created from templates and staffed
in the following quarter. The projects will need to remain in a backlog until the team has capacity to
work on them. There has been confusion previously because the team used Planning status for all
work not started.
What should the project manager do to help the team see the difference between work in the
backlog versus work that is now being planned?
Options