Question 6 Q: 6 Review the Version Report: Options A: The release date that has been added to this version should be reconsidered. B: More than 20 story points were burned when this chart was reviewed in July 2015. C: Only three issues have been completed in the version, so a predicted end date is not possible. D: The team should use time-based estimation, not story points. E: There are too many unestimated issues in this version, so any predictions are inaccurate. Save Question Show Answer Discussion 0 Clear Discussion Most voted Newest No comments yet. Be the first to comment. Post Be respectful. No spam. Correct Answer: B Explanation :