The Cumulative Flow Diagram is the report that provides the needed insight to see if frequent scope
change mid-sprint is causing bottlenecks. The Cumulative Flow Diagram shows the quantity and
distribution of work items along different stages of a process over time. The report can help identify
potential bottlenecks in the workflow by showing where work items accumulate or stagnate over
time. For example, if the report shows a sudden increase or a wide band of work items in the “In
Progress” stage, it may indicate that the team is overloaded with work or facing some blockers. If the
team often accepts new requests from outside groups during an active sprint, the report can show
how this affects the flow of work and the completion of the sprint goal. Reference: Managing Jira
Projects Data Center and Server: Certification Bundle, Cumulative Flow Diagram