Q: 16
Smith, the project manager for a larger multi-location firm, is leading a software project team that
has 18
members, 5 of which are assigned to testing. Due to recent recommendations by an organizational
quality audit
team, the project manager is convinced to add a quality professional to lead to test team at
additional cost to
the project.
The project manager is aware of the importance of communication for the success of the project and
takes the
step of introducing additional communication channels, making it more complex, in order to assure
quality
levels of the project. What will be the first project management document that Smith should change
in order to
accommodate additional communication channels?