Q: 9
Revision control is set at the organization level. Both Colorado and New York sites have item A under
revision control. Item A was shipped from the Colorado site to the New York site on Internal Order
using Revision B. Since that time, revision control at the Colorado site has been changed to a numeric
value and the current revision is 3. Now, New York is returning item A on an Internal Order with
Revision B. What would happen when Colorado attempts to receive this unit?
Options
Discussion
No comments yet. Be the first to comment.