HOTSPOT Column 1 is a list of entries from the Daily Log that occurred during stage 4 in the Controlling a Stage process. For each entry in Column 1, select the first management product from Column 2 that should have been updated, or created, as a result of the entry. Each selection from Column 2 can be used once, more than once or not at all. Drop down the right answer from column 1 to column 2. 
Free PRINCE2-Practitioner Practice Test Questions and Answers (2026)
HOTSPOT Product Summary A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers. Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries. The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page. Product Breakdown Structure (contains errors) 

DRAG DROP Project Scenario – Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers. ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver “capability to provide health and safety training”, including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents. The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company’s development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses. The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project. The ABC Company standard development model for new courses recommends the following stages: 
HOTSPOT The project has a cost tolerance of +5% I ·5%, of which stage 2 has a tolerance of +£45k 1-£45k. Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.
DRAG DROP INITIATING A PROJECT Here are three items of information relating to the ‘initiating a project’ process for the project. As part of which activity (A-F) should this information be recorded? Choose only one theme for each activity. Each theme can be used once, more than once, or not at all.
HOTSPOT Extract from the Project Product Description (with errors) 
DRAG DROP BUSINESS CASE Here are three statements from the business case for the Health and Safety Project. Under which heading in the business case (A-F) should they be recorded? Choose only one heading for each statement. Each heading can be used once, more than once, or not at all.
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC
Company has grown quickly into a successful training company. It delivers a range of accredited
professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing
budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and
monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training
development budget. His department organizes courses, venues and trainers. They work with the
Product and the Sales teams to provide a comprehensive training schedule. ABC Company’s IT
manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and
propose new products. She will work with the Operations. Director to ensure a cost-conscious
approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible
for developing training materials and gaining accreditation, in accordance with the standard course
development model. Course developers in his team have skills in a range of development
technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring
that internal and external trainers deliver ABC Company training courses to the required standard.
He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management
and configuration management. He recently led a project to consolidate all company quality systems
into one quality management system and set up a corporate quality department, now managed by
the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the
company’s document management system and now operates it across the business. She manages a
team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by
suggesting new markets for the courses and material. All account managers and the marketing team
report to him. They promote existing training courses to other training companies and existing
customers.
End of the additional information.
ABC Company carried out a similar project two years ago, in response to changes in health and safety
legislation for the health service. The experiences from that project were used to refine the
corporate risk management policy. For that reason, the project board decided to use the corporate
risk management policy in the risk management approach for this project.
Is this appropriate, and why?HOTSPOT Additional Information Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering are a. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required. Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image. Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar. Central Records: This group of five staff looks after all company records and document control. They now maintain all project files. Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project. Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet to be decided which of the photographers to use. Using the additional Information provided for this question In the Scenario Booklet, answer the following question. Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.
HOTSPOT The Calendar project was delivered as originally planned, and Is now preparing for planned closure. Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.
DRAG DROP Project Scenario – Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers. ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver “capability to provide health and safety training”, including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents. The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company’s development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses. The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project. The ABC Company standard development model for new courses recommends the following stages: 
HOTSPOT Scenario: Techniques, processes and procedures 1. Any threat that may result in a loss of MFH data must be escalated immediately. Joint agreements 2. Work is to start at the beginning of week 2 (Stage 4). 3. The project will take two years to complete, at an estimated cost of £2.5m. Tolerances 4. None. Constraints 5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment. 6. Installation work must take place during MFH normal working hours. 7. +£10,000 / -£25,000. Reporting arrangements 8. Highlight Report every Monday by 10.00 am. 9. The report must contain a summary of all products worked on during the previous week. 10. Project Manager must be notified of any issues immediately by telephone. Problem handling and escalation 11. Impact analysis of all issues must be completed within 24 hours. Extracts or references 12. The Stage Plan for stage 4 is available from Project Support. Approval method 13. Project Assurance will review the completed Work Package and confirm completion At the end of stage 3, the service provider will be selected and the contract awarded. During stage 4, the Account Manager for the selected service provider will work with the Project Manager to complete the transition of the services to the selected service provider.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used
the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes
the Business Case, a product checklist and several Product Descriptions, Including the Project Product
Description. Short sections are also included for each of the strategies and the controls to be applied.
The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality -
results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold regular
checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
This question provides a number of changes which may or may not be required to the Extract from
the Communication Management Strategy provided in the additional information.
Which statement applies to the Timing of communication activities section?What's covered in this practice questions set
4: Apply and tailor the PRINCE2 processes in context · 16 questions
📖 About this Domain
This domain tests your ability to apply the seven PRINCE2 processes to a given project scenario. It focuses on the practical execution of process activities and the tailoring of management products. You must demonstrate understanding of the entire project lifecycle from pre-project to final closure.
🎓 What You Will Learn
- You will learn to apply the activities within each of the seven processes, including Starting up a Project (SU), Initiating a Project (IP), and Closing a Project (CP).
- You will learn how to tailor the processes and their associated management products to fit the scale, complexity, and risk of a specific project.
- You will learn the specific responsibilities of the Project Manager, Project Board, and Team Manager within each process.
- You will learn the flow of management products between processes, such as the Project Brief from SU to IP or the End Stage Report from CS to SB.
🛠️ Skills You Will Build
- You will build the skill to analyze a project scenario and determine the appropriate process activities to execute.
- You will build the competence to justify tailoring decisions for processes and management products based on the project environment.
- You will build the ability to map project management team roles to specific process activities and responsibilities.
- You will build the practical skill of managing the project on a stage-by-stage basis using the CS, MP, and SB processes.
💡 Top Tips to Prepare
- Focus on the purpose and objectives of each of the seven processes, as this dictates their application in a scenario.
- Master the key inputs and outputs for each process, especially the creation and updating of management products like the PID and the Business Case.
- Use official PRINCE2 Practitioner exam sample papers to practice applying the processes to complex scenarios.
- Create diagrams or flowcharts to visualize the interaction between the processes, particularly the cycle between CS, MP, and SB.
3: Apply and tailor relevant aspects of PRINCE2 practices in context · 3 questions
📖 About this Domain
This domain tests your ability to practically apply the seven PRINCE2 practices to a given project scenario. It focuses on demonstrating how to tailor these practices, ensuring the method is appropriate for the project's specific environment and not applied rigidly.
🎓 What You Will Learn
- How to apply and tailor the Business Case and Organizing practices to establish project justification and a suitable project management team structure.
- Methods for applying and tailoring the Plans and Progress practices, including product-based planning and control using management by exception.
- Techniques for applying and tailoring the Risk and Issues practices to manage uncertainty and implement effective change control.
- Approaches to applying and tailoring the Quality practice to define acceptance criteria and implement appropriate quality management procedures.
🛠️ Skills You Will Build
- Analyzing a project scenario to determine the appropriate application and tailoring of each PRINCE2 practice.
- Justifying tailoring decisions for management products, roles, and procedures based on project context.
- Evaluating the effectiveness of the application of practices within a given scenario.
- Integrating the seven practices to ensure a coherent and controlled project management approach.
💡 Top Tips to Prepare
- Focus on the 'why' behind tailoring; always link your decisions back to the project's scale, complexity, risk, and environment.
- Practice with official scenario-based questions to master the application of practices, not just their theoretical definitions.
- Understand the minimum requirements for each practice to ensure your tailoring decisions do not compromise PRINCE2 compliance.
- Map the relationships between practices, such as how the Risk practice influences the Plans and Business Case practices.
1: Apply the PRINCE2 principles in context · 1 questions
📖 About this Domain
This domain assesses your ability to apply the seven guiding PRINCE2 principles within a project scenario. You must demonstrate how these principles are the bedrock of the methodology and are mandatory for a project to be managed using PRINCE2.
🎓 What You Will Learn
- You will learn to validate continued business justification throughout the project lifecycle.
- You will learn to integrate lessons learned from previous work and capture new lessons.
- You will learn to establish a clear project management team structure with defined roles and responsibilities.
- You will learn to apply the manage by stages principle for effective project board control points.
🛠️ Skills You Will Build
- You will build the skill to analyze a scenario and determine if a principle is being applied correctly.
- You will develop the ability to justify tailoring decisions based on the project environment and the principles.
- You will gain the competence to assess project viability by evaluating the application of all seven principles.
- You will learn to link project issues in a scenario back to the violation of a specific principle.
💡 Top Tips to Prepare
- Know all seven principles by name and their core purpose without hesitation.
- Practice identifying the interplay between principles and the seven themes in exam scenarios.
- Focus on keywords in the scenario that indicate a principle is being followed or ignored.
- Use official specimen papers to master how to connect scenario evidence to a specific principle.
2: Apply effective people management in successful projects
📖 About this Domain
This domain covers the people element central to the PRINCE2 method. It assesses your ability to apply concepts for leading and managing project teams effectively. You will analyze how human factors influence project success within the PRINCE2 integrated environment.
🎓 What You Will Learn
- You will learn to apply change management techniques to ensure user adoption and realize benefits.
- You will learn to apply leadership and management approaches to build and motivate the project management team.
- You will learn to tailor communication strategies for different stakeholders according to the communication management approach.
- You will learn to analyze and manage stakeholder interests and influence to support the project's business case.
🛠️ Skills You Will Build
- You will build the skill to identify and analyze stakeholder needs and expectations to inform project decisions.
- You will build the skill to apply situational leadership styles to manage team dynamics and performance.
- You will build the skill to integrate change management activities into the project lifecycle to overcome resistance.
- You will build the skill to develop and implement a communication management approach tailored to the project environment.
💡 Top Tips to Prepare
- Always relate people management concepts directly to the specific roles and situations described in the exam scenario.
- Understand the application of key models like Tuckman's stages of group development and the change curve.
- Connect people management activities to PRINCE2 principles and processes like 'initiating a project'.
- Repeatedly practice scenario-based questions that require choosing the most effective people management action for a given project issue.