Free Practice Test

Free PMP Practice Exam

Get ready for your PMP exam with our free, accurate, and 2025-updated questions.

Cert Empire is committed to providing the best and latest exam questions for those preparing for the PMI PMP exam. To assist students, we’ve made some of our PMP exam prep resources free. You can get plenty of practice with our Free PMP Practice Test.

Question 1

A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved. How should the project manager proceed?
Options
A: Proceed with both the prefeasibility and feasibility studies in parallel while waiting for (he final approvals
B: Include the feasibility activities in the prefeasibility study and apply for a change of scope and budget.
C: Obtain approval to proceed with the feasibility study as a parallel activity while the prefeasibility study is approved
D: Secure approval of the prefeasibility study before proceeding with the feasibility activities.
Show Answer
Correct Answer:
Obtain approval to proceed with the feasibility study as a parallel activity while the prefeasibility study is approved
Explanation
The scenario describes a need to perform project phases in parallel that would normally be done in sequence to maintain the timeline. This technique is known as fast-tracking. However, fast-tracking increases risk and requires the commitment of resources for a subsequent phase before the preceding phase is formally approved. Therefore, the project manager must adhere to the project governance framework and obtain explicit approval from the relevant authority (e.g., sponsor, steering committee) before starting the feasibility study activities. This action balances the need for schedule compression with responsible stakeholder management and risk control.
References

1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) (6th ed.).

Section 6.5.2.5, Schedule Compression: Defines fast-tracking as a technique where "activities or phases normally done in sequence are performed in parallel." The scenario directly calls for this technique.

Section 2.4.4.3, Project Governance: States that governance provides the framework for decision-making. Starting a new phase, especially under fast-tracking conditions, is a key decision that requires adherence to this framework, meaning approval must be sought.

2. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) (7th ed.).

Section 2.5, Planning Performance Domain: Notes that project life cycles can have "overlapping phases" to "shorten the project life cycle (i.e., fast tracking)." This validates the approach.

Section 2.1, Stakeholder Performance Domain: Emphasizes that effective stakeholder engagement, which includes seeking approvals for key decisions, is critical for project success. Proceeding without approval (Option A) would be poor stakeholder engagement.

3. Shenhar, A. J., & Dvir, D. (2007). Reinventing Project Management: The Diamond Approach to Successful Growth and Innovation. Harvard Business School Press.

This academic text discusses the importance of adapting project management style to the project's context. In time-critical projects, overlapping phases is a common strategy, but it must be a conscious, approved decision made within the project's governance structure to manage the associated risks. This supports seeking approval as the correct professional action.

Question 2

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?
Options
A: Ask the product owner if some low-priority stories could be cut from the sprint.
B: Continue with the sprint as the progress shows buffers for potential interruptions.
C: Ask the project team to select any additional stories as they have additional capacity than planned.
D: Continue with the sprint work as planned and keep monitoring.
Show Answer
Correct Answer:
Continue with the sprint work as planned and keep monitoring.
Explanation
The burndown chart indicates that the team is completing work faster than the ideal rate. However, it is only day four of a 15-day sprint. This early progress could be due to various factors, such as the team tackling easier tasks first. Making a significant change to the sprint scope, such as adding new stories, would be premature. The most appropriate and professional course of action is to continue with the current sprint plan while diligently monitoring the trend in the daily stand-ups. If the trend of being ahead of schedule continues consistently, the team can then discuss with the Product Owner about pulling in more work. This approach aligns with the agile principle of inspect and adapt based on sufficient data, rather than reacting to early, potentially misleading, indicators.
References

1. The Scrum Guide (2020): The purpose of the Daily Scrum is "to inspect progress toward the Sprint Goal and adapt the Sprint Backlog as necessary, adjusting the upcoming planned work." This supports the concept of ongoing monitoring and adaptation (Option D) rather than an immediate, major change to the backlog based on an early trend. Schwaber, K., & Sutherland, J. (2020). The Scrum Guide. Scrum.org. p. 10.

2. Agile Practice Guide (PMI): This guide describes burndown charts as a key tool for monitoring iteration progress. "Teams use this chart to track their progress and to see if they are on track to complete the work by the end of the iteration." A deviation from the ideal line is an indicator that requires the team's attention and continued monitoring to understand the trend before taking corrective or adaptive action. Project Management Institute. (2017). Agile Practice Guide. Section 5.2.4, "Measurements in Agile Projects," pp. 63-64.

3. University Courseware: In courses on Agile Development, it is taught that burndown charts are informational radiators that provide a forecast. A team's response to the data should be contextual. An early lead might not be sustainable, and the prudent action is to observe the trend over several days before altering the sprint commitment. This prevents thrashing and maintains focus on the original sprint goal. (e.g., concepts taught in courses like MIT's 6.893, "Engineering Interactive Technologies").

Question 3

DRAG DROP A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time. Match the roles for the team on the left to their corresponding responsibilities on the right. PMI PMP exam question

Show Answer
Correct Answer:

PRODUCT OWNER: DETERMINE THE VERSION OF THE PRODUCT THAT CAN BE RELEASED TO THE MARKET.

DEVELOPMENT TEAM: DETERMINE HOW TO ORGANIZE AND CARRY OUT WORK TO COMPLETE THE MINIMUM VIABLE PRODUCT (MVP).

PROJECT MANAGER/SCRUM MASTER: TAKE RESPONSIBILITY FOR REMOVING BLOCKERS THAT AFFECT THE TEAM'S PRODUCTIVITY.

Explanation

In the Scrum framework, roles are defined by their core responsibilities. The Product Owner is accountable for maximizing the value of the product and manages the Product Backlog, which includes making the final decision on what constitutes a releasable product version. The Development Team (referred to as Developers in the 2020 Scrum Guide) is a self-managing unit that has the autonomy to decide how to convert Product Backlog items into a finished increment. The Scrum Master acts as a servant-leader whose duties include removing impediments or "blockers" that hinder the Development Team's progress, thereby protecting their productivity.

References

Schwaber, K., & Sutherland, J. (2020). The Scrum Guide. Scrum.org.

Product Owner: "The Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team... For Product Owners to succeed, the entire organization must respect their decisions." (p. 6)

Development Team (Developers): "They are self-managing, meaning they internally decide who does what, when, and how." (p. 7)

Scrum Master: "The Scrum Master serves the Scrum Team in several ways, including: ... Causing the removal of impediments to the Scrum Teamโ€™s progress." (p. 8)

Sutherland, J., & Schwaber, K. (2013). The Scrum Papers: Nuts, Bolts, and Origins of an Agile Process. The Agile Software Development Series.

This collection reinforces the foundational roles, stating the ScrumMaster is "responsible for removing impediments to the teamโ€™s progress" and the Development Team is "self-organizing" and determines how to accomplish work.

MIT OpenCourseWare. (2013). 6.170 Software Studio, Lecture 5: Development Methods. Massachusetts Institute of Technology.

The course materials on Agile and Scrum outline these distinct roles, describing the Product Owner's responsibility for the product backlog and release decisions, the team's ownership of the implementation plan, and the Scrum Master's role in resolving obstacles.

Question 4

During execution of an agile project, a project manager realizes the budget is almost completely used, but the project is not close to being completed. What should the project manager do to address this concern?
Options
A: Review the project time line and find opportunities to reduce the project schedule.
B: Review the budget with the project sponsor and ask for an increase to the budget
C: Review the backlog and find opportunities to reprioritize the work and reduce the project scope
D: Review the resource management plan and find opportunities to reduce project costs.
Show Answer
Correct Answer:
Review the backlog and find opportunities to reprioritize the work and reduce the project scope
Explanation
In agile projects, scope is the primary variable that is adjusted to meet fixed constraints like budget and time. The product backlog is the ordered list of all work deemed necessary for the project. When the budget is nearly exhausted, the most appropriate agile practice is to work with the product owner and stakeholders to review the remaining items in the backlog. This allows the team to re-prioritize the work, focusing on delivering the highest-value features possible within the remaining budget. This may involve de-scoping lower-priority items to ensure a viable product is delivered, which aligns with the agile principle of maximizing value.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition.

Section 2.8.4, Planning Performance Domain, p. 99: "In adaptive approaches, the scope is defined and redefined throughout the project. The overall scope is decomposed into a set of requirements and work to be performed, which is sometimes referred to as a product backlog." This establishes the backlog as the primary tool for managing and adjusting scope.

2. Project Management Institute. (2017). Agile Practice Guide.

Section 5.2.3, The Iron Triangle in Agile Projects, p. 19: This section explains that in agile projects, cost and schedule are often fixed, while scope is variable. The guide states, "The team decides what can be done in the given time box... The scope is variable." This directly supports adjusting scope (the backlog) when a constraint like budget is hit.

Section 4.2.2, Backlog Refinement, p. 52: "The product owner is responsible for prioritizing the backlog to maximize the value of the product... This includes adding, removing, and reprioritizing items." This confirms that re-prioritizing the backlog is the correct mechanism for managing the work.

3. Serrador, P., & Pinto, J. K. (2015). Does Agile work?โ€”A quantitative analysis of agile project success. International Journal of Project Management, 33(5), 1040-1051.

p. 1048: The study finds that agile planning, which includes iterative scope adjustment and prioritization, is a significant predictor of project success, particularly in managing budget and stakeholder satisfaction. This reinforces the idea that flexible scope management is a key control for budget adherence. (https://doi.org/10.1016/j.ijproman.2015.01.006)

Question 5

A project team is struggling to obtain the required data for a complex project in order to proceed to the next stage. What should the project manager do?
Options
A: Set up a meeting with the team to discuss and determine the project's challenges.
B: Propose a revised project schedule to the sponsor as the delays have affected the time lines.
C: Schedule a meeting with the sponsor to express the team's frustrations about the data.
D: Meet with the data suppliers to explain the critical timing requirements of the project.
Show Answer
Correct Answer:
Meet with the data suppliers to explain the critical timing requirements of the project.
Explanation
The project manager's primary responsibility is to proactively identify and remove impediments that are blocking the project team's progress. The core issue is the failure to obtain necessary data, which is a critical dependency. The most effective and direct course of action is to engage with the source of the dependencyโ€”the data suppliers. By meeting with them, the project manager can communicate the urgency, clarify requirements, and collaborate on a solution to resolve the data delivery issue, thereby removing the blocker for the team.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition.

Section 2.8, Project Work Performance Domain: This domain addresses "managing impediments, obstacles, and blockers." The guide states, "The project manager and project team facilitate the proactive management of impediments, risks, and issues to keep the project on track." (p. 91). Meeting the supplier is a proactive action to manage an impediment.

2. Project Management Institute. (2017). Agile Practice Guide.

Section 5.2.4, Servant Leadership Empowers the Team: This section emphasizes the leader's role in problem-solving. "Servant leaders facilitate problem-solving... by opening up communication channels and by helping people to collaborate... They remove impediments, obstacles, and blockers." (p. 35). The lack of data is a blocker, and engaging the supplier is a direct attempt to remove it.

3. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition.

Section 2.3, Stakeholder Performance Domain: This domain covers working with stakeholders to maintain alignment. Data suppliers are key stakeholders. The guide notes, "Effective stakeholder engagement involves implementing strategies and actions to promote the productive involvement of stakeholders." (p. 67). Meeting with the suppliers is a direct engagement strategy.

Question 6

A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch However, the company sees a great demand for this product and wants it to launch as soon as possible. What should the project manager do to realize this opportunity?
Options
A: Communicate with the industry's regulatory authority to grant the company an exception
B: Escalate the issue to the company's CEO who has experience with the regulations.
C: Comply with the regulatory requirements and work to compress the project schedule.
D: Hire a third party who is an expert on the industry's regulations to work out the details.
Show Answer
Correct Answer:
Comply with the regulatory requirements and work to compress the project schedule.
Explanation
The project manager's primary responsibility is to deliver the project within its defined constraints, which include mandatory legal and regulatory requirements. Compliance is non-negotiable. To address the business need for an accelerated launch, the project manager should employ schedule management techniques. Schedule compression, which includes methods like crashing (adding resources) or fast-tracking (performing activities in parallel), allows the project team to shorten the overall project duration while still completing all necessary steps, including the full regulatory process. This approach directly addresses both the compliance constraint and the time-to-market opportunity.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Section 2.4, Planning Performance Domain. This domain addresses the activities needed to organize and coordinate the project work. It includes developing a schedule, which can be optimized using techniques like schedule compression to meet time constraints.

2. Project Management Institute. (2021). The Standard for Project Management (ANSI/PMI 99-001-2021). Section 3.5, Tailoring. This section explains that the project manager must tailor the project approach based on various factors, including "compliance requirements." The standard emphasizes that projects operate within internal and external environments, and compliance with regulations is a key external factor that cannot be ignored.

3. Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). Wiley. Chapter 12, "Scheduling," discusses schedule compression techniques such as crashing and fast-tracking as standard methods for shortening a project schedule when faced with time constraints, while still adhering to project scope and quality requirements.

Question 7

A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule. What should be me project manager's response?
Options
A: Sprint plan and product roadmap
B: Product roadmap and sprint backlog
C: Product backlog and scrum board
D: Sprint backlog and scrum board
Show Answer
Correct Answer:
Sprint plan and product roadmap
Explanation
In Scrum the function of a traditional project schedule is conveyed at two time-horizons. โ€ข Product roadmap (or release roadmap) gives the long-range, calendar-oriented view of when major features or releases are expected. โ€ข Sprint plan (the outcome of Sprint Planning) provides the short-range, iteration-level forecast of work that the team commits to complete in the current time-box. Together they fulfil the same purpose as a predictive scheduleโ€”establishing both overall timeline and near-term tasksโ€”while maintaining agility.
References

1. PMI โ€“ Agile Practice Guide, 1st ed., 2017:

โ€ข ยง3.4.1 โ€œProduct Roadmapโ€, p. 44 โ€“ defines roadmap as a high-level time-based view replacing traditional schedules.

โ€ข ยง3.4.3 โ€œIteration (Sprint) Planโ€, p. 45 โ€“ identifies sprint plan as the short-term scheduling mechanism.

2. PMI โ€“ PMBOKยฎ Guide, 7th ed., 2021:

โ€ข ยง4.3 โ€œPlanning Performance Domainโ€, p. 59 โ€“ notes that agile teams use roadmaps and iteration plans instead of detailed schedules.

3. Rubin, K. S., โ€œEssential Scrumโ€, Addison-Wesley, 2012:

โ€ข Ch. 14 โ€œThe Product Roadmapโ€, pp. 273-275 โ€“ describes roadmap as Scrumโ€™s long-range schedule.

โ€ข Ch. 17 โ€œSprint Planningโ€, p. 320 โ€“ positions the sprint plan as the detailed schedule for a single iteration.

Question 8

A telecommunications project consists of departments spread across several countries with different cultures. The project team rarely meets in person, and each team member works independently using online reporting tools. What should the project manager do to ensure team members are committed to project success?
Options
A: Control and follow the project's mam goals, budget, and schedule
B: Plan regular virtual meetings to motivate and support the team.
C: Meet in small groups and share information by email with the rest of the team
D: Create a monthly report so everyone will be informed of the current status.
Show Answer
Correct Answer:
Plan regular virtual meetings to motivate and support the team.
Explanation
In a geographically dispersed and culturally diverse virtual team, fostering a sense of unity and shared purpose is critical for commitment. Regular virtual meetings provide a forum for two-way communication, which is essential for building relationships, clarifying goals, resolving misunderstandings, and providing mutual support. This proactive engagement helps overcome the isolation inherent in virtual work, motivating team members and aligning them toward project success. This aligns with the project manager's role as a leader in developing and managing the project team.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Project Management Institute.

Section 2.4, Team Performance Domain (p. 72): This section emphasizes that for virtual teams, "establishing regular and effective communication is critical." It highlights that leadership activities, including facilitating team development and communication, are key to creating a cohesive and high-performing team. Option B directly implements this principle.

2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Sixth Edition. Project Management Institute.

Section 10.1.2.4, Communication Methods (p. 374): This section distinguishes between interactive communication (like meetings), push communication (like reports), and pull communication. It states that interactive communication is the most effective way to ensure a common understanding, which is fundamental to team commitment. Option B uses an interactive method, whereas Option D uses a less effective push method.

3. Hertel, G., Geister, S., & Konradt, U. (2005). Managing virtual teams: A review of current empirical research. Human Resource Management Review, 15(1), 69-95.

Section 3.1, Communication (p. 79): This peer-reviewed article synthesizes research on virtual teams and concludes that the frequency and quality of communication are significant predictors of team performance and cohesion. Regular meetings (Option B) directly increase the frequency and potential quality of team interaction. (https://doi.org/10.1016/j.hrmr.2005.01.007)

Question 9

A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist from the team was average. What should the project manager do to help the new compliance specialist improve?
Options
A: Escalate this situation to the manager of the area for a possible solution.
B: Provide time for the specialist to adjust to the pace of the project.
C: Coordinate a one-to-one meeting with the specialist to assess the situation.
D: Contact the human resources (HR) manager about the team's feedback.
Show Answer
Correct Answer:
Coordinate a one-to-one meeting with the specialist to assess the situation.
Explanation
The project manager's role includes team leadership and development. The most appropriate initial action when receiving performance feedback is to engage directly and privately with the team member. A one-to-one meeting allows the project manager to assess the situation from the specialist's perspective, understand any challenges they may be facing, provide constructive feedback, and collaboratively determine the best path for improvement. This approach is proactive, supportive, and aligns with the principles of servant leadership, focusing on enabling team members to succeed. Escalating the issue to functional management or HR before a direct conversation is premature and can undermine trust.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition.

Section 2.4, Team Performance Domain, p. 43: This domain emphasizes that "Project team development is the process of improving the competencies, team member interaction, and overall team environment to enhance project performance." Directly meeting with the specialist is a core activity in team development.

Section 2.4.3, Leadership Skills, p. 45: Effective leaders "look for opportunities to serve others" and "demonstrate empathy." Assessing the situation in a one-to-one meeting is a direct application of these servant leadership skills.

2. Project Management Institute. (2017). Agile Practice Guide.

Section 5.1.1, Servant Leadership, p. 34: Servant leaders "help the team with problem identification and problem solving." The project manager should first seek to understand the problem by speaking with the specialist before taking other actions.

3. Mรผller, R., & Turner, J. R. (2010). Leadership competency profiles of successful project managers. International Journal of Project Management, 28(5), 437-448.

p. 443: The study identifies "engaging communication" and "developing others" as key competencies for successful project managers. Coordinating a one-to-one meeting to assess a situation and help an employee improve is a direct application of these competencies. (DOI: https://doi.org/10.1016/j.ijproman.2009.09.003)

Question 10

A project manager is closing a project and preparing to hand it over to the operations team. During handover, a delayed invoice was submitted with a higher-than-planned cost against the project work. Consequently, project handover was delayed and the project's reported completion costs were increased. What should the project manager have done to avoid this situation?
Options
A: Captured and reviewed all of the project work and related costs regularly
B: Notified all vendors about the invoicing and nonpayment deadlines
C: Reviewed the total committed cost against the cost invoiced at project closing
D: Involved the finance team and discussed the issue with the vendor
Show Answer
Correct Answer:
Captured and reviewed all of the project work and related costs regularly
Explanation
The core issue is a failure in the ongoing monitoring and control processes. The Control Costs process requires the project manager to regularly monitor project status, compare actual costs to the baseline, and manage changes. By "capturing and reviewed all of the project work and related costs regularly," the project manager would have maintained an accurate picture of financial commitments and expenditures. This proactive, continuous oversight would have identified the outstanding invoice and the potential cost variance long before the closing phase, allowing for timely corrective action and preventing the last-minute surprise that delayed the project handover.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition.

Section 2.7, Measurement Performance Domain: This domain emphasizes assessing project performance and taking appropriate actions. It states, "Effective execution of this performance domain includes the continual evaluation of project performance for cost..." (p. 99). This supports the need for regular review as described in option A.

2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Sixth Edition.

Section 7.4, Control Costs: This process is defined as "monitoring the status of the project to update the project costs and managing changes to the cost baseline." A key benefit is that it "provides the means to recognize variance from the plan in order to take corrective action and minimize risk." This directly aligns with the preventative action in option A.

3. Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). Wiley.

Chapter 15, Cost Control: This chapter details that a primary objective of a cost control system is the "early identification of problems" (p. 535). It emphasizes that cost control is a continuous process of comparing actual costs with planned costs and reporting variances in a timely manner to allow for corrective action. This principle directly supports the regular review mentioned in option A.

Question 11

The project manager is reviewing a project's progress and notices that one of the risks has become an issue. What should the project manager do to address the situation?
Options
A: Schedule a high-priority meeting with the project stakeholders to discuss the issue.
B: Initiate a change request to obtain additional funds from the management reserve.
C: Meet with the project team and customer to brainstorm about potential solutions.
D: Collaborate with the relevant stakeholders on implementing the risk response plan.
Show Answer
Correct Answer:
Collaborate with the relevant stakeholders on implementing the risk response plan.
Explanation
When a known risk occurs, it becomes an issue. The proper project management process is to execute the pre-defined risk response plan that was developed during the planning phase. This proactive approach ensures that agreed-upon strategies and actions are implemented promptly to manage the situation. The "Implement Risk Responses" process is triggered by the occurrence of such a risk. The project manager's role is to lead and collaborate with the relevant stakeholders to carry out the planned actions, thereby controlling the impact on the project's objectives.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Project Management Institute, Inc. Section 2.7, "The Uncertainty Performance Domain," discusses the need to implement agreed-upon risk responses when a risk occurs.

2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Sixth Edition. Project Management Institute, Inc. Section 11.6, "Implement Risk Responses," states, "Implement Risk Responses is the process of implementing agreed-upon risk response plans." The key input for this process is the risk response plan, and it is triggered when a risk event occurs.

3. Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). Wiley. Chapter 18 on Risk Management details that the execution of risk handling plans is the critical step following risk monitoring and control when a trigger event happens.

Question 12

A company is using an agile approach to launch a new product. In the second sprint, the team encounters a technical problem they have never faced before. What should the project manager do?
Options
A: Inform the project sponsor about the problem faced by the team.
B: Ask the product owner to write the specifications for the related user story.
C: Organize an early retrospective with the team to analyze the problem.
D: Facilitate a problem-solving session with the team to analyze the problem.
Show Answer
Correct Answer:
Facilitate a problem-solving session with the team to analyze the problem.
Explanation
In an agile framework, the project manager often serves as a facilitator or servant-leader. Their primary responsibility is to empower the team and remove impediments. When a new technical problem arises, the most effective and agile-aligned action is to facilitate a collaborative session. This approach leverages the collective knowledge of the development team, who are the technical experts, to analyze the problem and devise a solution. It supports the agile principles of self-organization, team ownership, and direct communication. The project manager's role is to guide this process, ensuring the team has the structure and support needed to resolve the challenge efficiently, rather than solving it for them or escalating prematurely.
References

1. Project Management Institute. (2017). Agile Practice Guide. Section 4.3, Servant Leadership, pp. 33-35. This section details the servant-leader's role in facilitating, coaching, and removing impediments for the team.

2. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Section 2.7.2, Project Team. This section emphasizes the project team's accountability and the project manager's role in fostering a collaborative environment for problem-solving.

3. Hoda, R., & Noble, J. (2017). Becoming a good scrum master: A reflective practice perspective. Proceedings of the 10th International Conference on Cooperative and Human Aspects of Software Engineering, 1-10. This paper highlights the scrum master's (an agile project manager role) function as a facilitator who guides the team through challenges. https://doi.org/10.1145/3054257.3054258

Question 13

During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the quality standards required by regulations. What should the project manager have done to avoid this?
Options
A: Reviewed with the product owner that all the stories worked on in the iteration were in the project backlog
B: Ensured that the project sponsor understood the scope of the project to avoid any future complaints
C: Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration
D: Ensured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks
Show Answer
Correct Answer:
Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration
Explanation
The rejection occurred because the product failed to meet regulatory quality standards. In an agile or hybrid environment, specific requirements, including quality and regulatory standards, are defined as acceptance criteria for each user story. The product owner is responsible for ensuring these criteria are met before accepting a story as "done." The project manager should have facilitated this process, ensuring a thorough review with the product owner against the acceptance criteria before the system demo. This proactive verification would have identified the non-compliance, allowing the team to address it and preventing the stakeholder's rejection during the public demonstration.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition.

Section 2.4, Delivery Performance Domain: This domain addresses the activities and functions associated with delivering the project's scope and quality. Section 2.4.2 on Quality states, "Acceptance criteria can be used to ensure the project deliverables meet stakeholders' requirements." This directly links acceptance criteria to meeting stakeholder quality expectations.

2. Project Management Institute. (2017). Agile Practice Guide.

Section 4.2.3, Backlog Refinement: This section explains that during backlog refinement, "The team clarifies requirements and defines acceptance criteria." It emphasizes that these criteria are essential for understanding and completing the work correctly.

Section 5.2.3, Work in Progress: This section describes the flow of work. A key concept is that a story is not considered "done" until it meets all of its acceptance criteria and is formally accepted by the product owner. This acceptance step is the critical quality gate that was missed in the scenario.

3. Serrador, P., & Pinto, J. K. (2015). Does Agile work? โ€” A quantitative analysis of agile project success. International Journal of Project Management, 33(5), 1040-1051. https://doi.org/10.1016/j.ijproman.2015.01.006

This study highlights that a key success factor in agile projects is a clear definition of requirements and a shared understanding of "done." The paper implicitly supports the idea that well-defined and verified acceptance criteria (a core agile practice) are crucial for meeting stakeholder expectations and achieving project success, thereby avoiding situations like the one described.

Question 14

A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another. What should the project manager do?
Options
A: Ask the experienced members to lead the junior members to facilitate skill transfer.
B: Encourage team members to focus on delivering results with their specialized skills.
C: Organize networking sessions to allow the team members to get to know one another.
D: Ask the team to self-organize and escalate any issues to the project manager.
Show Answer
Correct Answer:
Organize networking sessions to allow the team members to get to know one another.
Explanation
The project manager's primary role in this situation is to act as a facilitator and leader to build a cohesive team. The identified problem is a communication and collaboration gap rooted in a lack of familiarity between new and long-term employees. Organizing networking sessions is a direct team-building activity that addresses this root cause. It creates opportunities for informal interaction, helping to build trust, establish personal relationships, and foster a shared team identity. This foundation of mutual understanding is essential for improving professional communication and collaboration, directly aligning with the goal of creating a high-performing team.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Project Management Institute.

Section 2.2, Project Team Performance Domain: This section emphasizes that "A project team is a group of individuals who work together to achieve a common goal." It further explains that developing a team culture involves creating an environment of "trust, respect, and transparency." Organizing networking sessions is a direct method for fostering such an environment.

2. Project Management Institute. (2017). Agile Practice Guide. Project Management Institute.

Section 4.2, Servant Leadership Empowers the Team: This section highlights the project manager's role in "building a safety net" and "creating an environment of trust." Facilitating activities that allow team members to get to know each other is a core component of building this trust.

3. Salas, E., Shuffler, M. L., Thayer, A. L., Bedwell, W. L., & Lazzara, E. H. (2015). Understanding and improving teamwork in organizations: a scientifically based practical guide. Human Resource Management, 54(4), 599โ€“622.

DOI: https://doi.org/10.1002/hrm.21628

This article (p. 607) discusses the importance of "interpersonal processes" for effective teamwork, which include conflict management, motivation, and confidence building. Networking and social events are practical tools for improving these interpersonal dynamics, which are currently lacking in the described team.

Question 15

A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO) needs visibility of the regulatory constraints while maintaining a degree of flexibility. Which tool can the project manager use?
Options
A: Use a burndown chart to provide transparency.
B: Use a kanban board to increase accountability.
C: Use a product backlog to manage changes.
D: Use a burnup chart to provide transparency.
Show Answer
Correct Answer:
Use a product backlog to manage changes.
Explanation
The product backlog is the most suitable tool for this scenario. It is a dynamic and ordered list of all requirements, features, and constraints for the project. In a regulated environment that is expected to change, new or modified regulatory constraints can be added to the backlog as work items (e.g., user stories or compliance tasks). This makes the constraints visible to all stakeholders, including the PMO. The backlog is designed to be continuously refined and re-prioritized, which provides the essential flexibility needed to adapt to the evolving regulatory landscape.
References

1. Project Management Institute. (2017). Agile Practice Guide.

Section 4.2.4, Backlog: "The backlog is an ordered list of all the work, presented in story form, for a team... The backlog is a living artifact. It is dynamic and is constantly updated with new items." This supports its use for managing changing requirements and constraints.

Section 5.2.4, Backlog Refinement: This section describes the process of adding detail, estimates, and order to backlog items, highlighting its role in adapting to new information and maintaining flexibility.

2. Schwaber, K., & Sutherland, J. (2020). The Scrum Guide.

Page 6, Product Backlog: "The Product Backlog is an emergent, ordered list of what is needed to improve the product. It is the single source of work undertaken by the Scrum Team." This establishes the backlog as the central, visible repository for all work, including compliance and regulatory items.

3. Layton, M. C., & Ostermiller, S. J. (2017). Agile Project Management For Dummies. John Wiley & Sons.

Chapter 6, The Product Backlog: This chapter explains that the product backlog contains all requirements and that its prioritized and dynamic nature allows project teams to respond to changes, including those from external factors like regulations, providing both visibility and flexibility.

Question 16

Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome. What should the project manager have done to prevent this situation?
Options
A: Performed a stakeholder analysis when the sponsor joined the project
B: Held a governance meeting to review the project increment
C: Conducted a product iteration review with the new project sponsor
D: Escalated the issue to ensure the increment would be approved
Show Answer
Correct Answer:
Performed a stakeholder analysis when the sponsor joined the project
Explanation
The root cause of the problem is the misalignment of a new, key stakeholderโ€”the project sponsor. To prevent such a situation, a project manager must be proactive. When a new sponsor joins, the immediate and essential action is to perform a stakeholder analysis. This process involves identifying their expectations, influence, interest, and communication requirements. The results of this analysis would enable the project manager to develop an effective engagement strategy to align the new sponsor with the project's history, objectives, and progress, thereby preventing misunderstandings and rejections of project artifacts and increments.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Project Management Institute, Inc.

Section 2.5, Stakeholder Performance Domain: This domain emphasizes that effective stakeholder interaction is critical for project success. It states, "Stakeholder engagement includes implementing strategies and actions to promote productive involvement of stakeholders." When a key stakeholder changes, this necessitates a re-evaluation and adjustment of engagement strategies.

2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Sixth Edition. Project Management Institute, Inc.

Section 13.1, Identify Stakeholders: This process is not a one-time activity. The guide states, "It is important to identify stakeholders... and to analyze and document relevant information... This process is performed periodically throughout the project as needed." The arrival of a new sponsor is a critical trigger to re-perform this process.

Section 13.2, Plan Stakeholder Engagement: The key benefit of this process is providing "an actionable plan to interact effectively with stakeholders." This plan is based on the analysis of stakeholder needs and expectations.

3. Aaltonen, K., & Kujala, J. (2010). A project lifecycle perspective on stakeholder influence strategies in global projects. Scandinavian Journal of Management, 26(4), 381-397. https://doi.org/10.1016/j.scaman.2010.09.001

This publication underscores that stakeholder analysis and engagement strategies must be adapted throughout the project lifecycle as the stakeholder environment changes, which includes the replacement of key individuals like a project sponsor.

Question 17

A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach. Why did the project manager choose a hybrid approach?
Options
A: A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties.
B: A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions.
C: A hybrid approach will allow the project manager to revise the product specifications.
D: A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction.
Show Answer
Correct Answer:
A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction.
Explanation
The scenario presents two distinct challenges: high uncertainty in requirements ("product definitions and requirements are still not clear") and a significant constraint ("product delivery for a specific date due to a regulatory requirement"). A hybrid approach is chosen specifically to address this duality. The adaptive (Agile) components of the hybrid model are used to manage the evolving requirements through iterative development and feedback. Simultaneously, the predictive (Waterfall) components provide a high-level framework, milestones, and control mechanisms to ensure the project progresses toward the fixed regulatory deadline. This blend leverages the strengths of both methodologies to fit the project's unique context.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Project Management Institute, Inc. Section 2.5.3, "The Delivery Approach and Life Cycle Relationship," explains that the choice of a delivery approach depends on the project's characteristics. A hybrid approach is suitable for projects with elements of uncertainty (like requirements) combined with constraints (like schedule or budget).

2. Project Management Institute & Agile Alliance. (2017). Agile Practice Guide. Project Management Institute, Inc. Section 3.3, "Characteristics of Hybrid Life Cycles," states that hybrid life cycles are a combination of predictive and adaptive approaches. This is useful when there is uncertainty, but also a need for formal tracking against a plan, which is essential for meeting a regulatory deadline.

3. Shenhar, A. J., & Dvir, D. (2007). Reinventing Project Management: The Diamond Approach to Successful Growth and Innovation. Harvard Business School Press. Chapter 4 discusses tailoring project management approaches based on novelty, technology, complexity, and pace. The principles support combining structured, goal-oriented planning (for the deadline) with flexible, iterative execution (for the unclear requirements).

Question 18

A medium-sized company has been exploring new marketing tactics with regard to launching a new product. New product creation is no small task. In the end, it was too big of an expenditure for the company to undertake. What should the project manager do in the future when working on new product projects?
Options
A: Make use of kanban boards so all stakeholders have a clear view of the project and provide their help accordingly.
B: Increase the contingency reserve and prepare the team for applying fast-failing techniques when the estimates veer from the initial plan.
C: Adopt a chain management approach, developing products based on the same platform and infrastructure.
D: Train the team to first find the minimum viable product (MVP) that will deliver value to the customer.
Show Answer
Correct Answer:
Train the team to first find the minimum viable product (MVP) that will deliver value to the customer.
Explanation
The primary issue identified is that the new product creation was "too big of an expenditure." This indicates a problem with the initial scope and investment size. The Minimum Viable Product (MVP) approach directly addresses this by focusing on developing the smallest version of the product that provides tangible value to early customers. This allows the organization to launch with a significantly lower initial cost, test market hypotheses, and gather validated learning. Future development can then be guided by real user feedback, reducing the risk of building a large, expensive product that nobody wants. This iterative strategy is a cornerstone of modern adaptive and agile project management for new product development.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Project Management Institute.

Section 4.5.2, Methods: This section discusses common methods, including iterative and incremental approaches. The MVP is a key concept within these methods, used to deliver value in small increments and obtain feedback, which is crucial when uncertainty is high, as in new product development.

2. Project Management Institute. (2017). Agile Practice Guide. Project Management Institute.

Section 5.2.5, Minimum Viable Product (MVP): This section explicitly defines the MVP as a strategy to "learn with the least amount of effort." It emphasizes releasing a minimal version to test a business hypothesis, directly countering the problem of undertaking an excessively large initial expenditure.

3. Ries, E. (2011). The Lean Startup: How Today's Entrepreneurs Use Continuous Innovation to Create Radically Successful Businesses. Crown Business.

While a business book, its principles are foundational to modern project management and are referenced in PMI materials. The concept of the MVP is central, defined as the version of a new product that allows a team to collect the maximum amount of validated learning about customers with the least effort (Chapter 6). This directly addresses the scenario's problem.

4. Lenarduzzi, V., & Taibi, D. (2016). MVP Explained: A Systematic Mapping Study. 2016 42th Euromicro Conference on Software Engineering and Advanced Applications (SEAA), pp. 112-119.

DOI: https://doi.org/10.1109/SEAA.2016.56

This academic paper analyzes the MVP concept, confirming its purpose is to reduce waste and test business hypotheses early in the development cycle, which aligns with solving the problem of excessive initial project expenditure.

Question 19

A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of the team. What should the project manager do?
Options
A: Move the task to the next sprint.
B: Ask the team member to bring up the concern in the next daily meeting.
C: Send an email explaining the issue to all team members.
D: Reassign the task to another team member.
Show Answer
Correct Answer:
Ask the team member to bring up the concern in the next daily meeting.
Explanation
In agile methodologies, the project manager's role is often that of a servant leader or facilitator who empowers the team. The daily meeting (or daily scrum) is the prescribed event for the team to synchronize activities and identify any impediments or obstacles. By advising the team member to raise the issue in the next daily meeting, the project manager promotes transparency, accountability, and collective ownership. This allows the entire team to become aware of the potential problem and collaboratively devise a solution, such as swarming on the task or re-planning, which aligns with the agile principle of self-organizing teams.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition.

Section 2.8, Project Work Performance Domain, p. 103: "Agile approaches use short feedback loops, adaptation, and frequent delivery... Daily standups are used to communicate progress, identify impediments, and coordinate the dayโ€™s work." This reference establishes the daily standup as the correct forum for identifying impediments.

2. Project Management Institute. (2017). Agile Practice Guide.

Section 5.2.3, Daily Standups, p. 54: "The purpose of the daily standup is to inspect progress toward the iteration goal and to adapt... The team can discuss... any impediments to progress." This explicitly states that impediments are a key topic for the daily standup.

Section 4.3.1, Servant Leadership Empowers the Team, p. 34: "Servant leaders... facilitate the removal of impediments, obstacles, and blockers for the team." Encouraging the use of the proper forum (the daily meeting) is a key facilitation activity.

3. Stray, V., Sjรธberg, D. I., & Dybรฅ, T. (2016). The daily stand-up meeting: A grounded theory study. Journal of Systems and Software, 114, 101-124.

Section 4.1, Core activities in the meeting, p. 107: The study identifies "Raising impediments" as a core activity of the daily stand-up meeting, where team members are expected to voice problems so the team or scrum master can address them. This academic source confirms the meeting's function in impediment management. (https://doi.org/10.1016/j.jss.2016.01.004)

Question 20

A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones. When will the project manager be able to provide the requested information?
Options
A: During the planning phase, when processes for scope definition and activity duration and sequencing will be performed
B: As soon as possible, as project delays can be significantly avoided when a schedule is developed early
C: Close to the end of the project, as the forecasts will be more accurate and most risks will already be mitigated
D: In the initiation process, as it happens concurrently with the project contract and project charter creation
Show Answer
Correct Answer:
During the planning phase, when processes for scope definition and activity duration and sequencing will be performed
Explanation
Concrete milestone dates are determined during the development of the project schedule. This is a core activity within the Planning Process Group. Before a reliable schedule can be created, the project manager must lead the team through several preceding planning processes. These include defining the scope, creating the Work Breakdown Structure (WBS), defining and sequencing activities, and estimating activity durations. These processes provide the necessary inputs for the Develop Schedule process, which outputs the project schedule with specific dates for milestones. Attempting to provide these dates during initiation would be premature and based on insufficient information, especially for a complex project.
References

1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Sixth Edition. Section 6.5, Develop Schedule. The guide states that the schedule is developed after activities are defined, sequenced, and their durations are estimated, all of which are part of the Planning Process Group. The inputs listed for the Develop Schedule process (e.g., Scope Baseline, Activity List, Activity Duration Estimates) are outputs from other planning processes.

2. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Section 2.4, Planning Performance Domain. This section explains that planning involves the "elaboration of information to the extent necessary to establish a consolidated approach to the project." It explicitly includes activities like estimating durations and developing a schedule (p. 71).

3. Meredith, J. R., Shafer, S. M., Mantel, Jr., S. J., & Sutton, M. M. (2017). Project Management: A Managerial Approach (10th ed.). Wiley. Chapter 6, "Project Planning," details that the creation of a detailed schedule and the identification of milestones are fundamental components of the planning phase, following the initial project launch or initiation.

Question 21

A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages. What should the project manager do?
Options
A: Communicate the risk to the steering committee and request a mitigation plan from senior management.
B: Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register.
C: Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders.
D: Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders.
Show Answer
Correct Answer:
Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders.
Explanation
According to the Project Management Institute (PMI), risk management is an iterative process that continues throughout the project life cycle. When a new risk is identified, the first step is to formally document it by adding it to the risk register. This ensures the risk is captured within the project's formal management system. Subsequently, the project manager must engage the project team and relevant stakeholders to analyze the risk (qualitatively and/or quantitatively) and plan an appropriate response. This reevaluation ensures the risk register remains a current and effective tool for managing project uncertainty.
References

1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) (6th ed.). Section 11.2, Identify Risks. This section describes "Identify Risks" as an iterative process, stating, "New risks may be identified as the project progresses through its life cycle." The primary output is the risk register, which is continuously updated.

2. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) (7th ed.). Section 2.8, Uncertainty Performance Domain. This section emphasizes that "New risks can be identified at any time during the project," necessitating a continuous process of identification, evaluation, and response planning.

3. Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). Wiley. Chapter 18 discusses the risk management process, highlighting that risk identification is not a one-time event but a continuous activity, requiring the risk register (or risk log) to be updated whenever new risks are discovered.

Question 22

A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change requests issued due to the nature of the project. What should the project manager do?
Options
A: Add a fixed number of change requests allowed by the client on the project baseline.
B: Request sponsor approval for all change requests to reduce the number of changes.
C: Initiate the number of iterations to reduce the number of change requests.
D: Reduce the number of approvers required to implement a change request.
Show Answer
Correct Answer:
Initiate the number of iterations to reduce the number of change requests.
Explanation
The project is characterized by innovation and a high level of uncertainty, which naturally leads to a high volume of changes. In such environments, a predictive (waterfall) approach with a formal change control process becomes burdensome. The most effective strategy is to adopt an adaptive or iterative life cycle. By working in iterations (or sprints), the project team can deliver value in small increments, gather feedback, and incorporate changes into the plan for subsequent iterations. This approach embraces change as a natural part of the discovery process, effectively managing the high volume of requests by building them into the project's rhythm rather than treating each as a formal exception.
References

1. Project Management Institute. (2017). Agile Practice Guide.

Section 3.1, Characteristics of Project Life Cycles, p. 19: "Iterative and incremental life cycles are the preferred approach when there is a high degree of change and a need to see at least a partial solution in a functional state." This directly supports using iterations to manage high-change environments.

Section 5.2.5, Retrospective, p. 50: Iterative approaches use retrospectives to "review and improve the process," which includes how changes and new requirements are handled in subsequent iterations.

2. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition.

Section 2.5, Project Management Principles, "Embrace adaptability and resiliency," p. 32: "An overall approach that is adaptable and resilient helps the project accommodate impacts and thrive. This is often accomplished through iterative or incremental approaches..." This principle advocates for the approach described in option C for uncertain projects.

Section 4.3, Models, Methods, and Artifacts, "Commonly Used Development Approaches," p. 175: This section describes how iterative development involves repeating activities in cycles to add functionality, which is a mechanism for incorporating the frequent changes expected in an innovative project.

Question 23

A customer complains that the user stories released so far contain too much jargon and do not reflect the expectations of the product. What should the project manager do next?
Options
A: Request approval from the company director to conduct training for the team.
B: Ask the senior developer to rewrite all the stories.
C: Engage with the customer and rewrite all the stories.
D: Rewrite the stories to include the technical vision of the product.
Show Answer
Correct Answer:
Engage with the customer and rewrite all the stories.
Explanation
The core issue is a misalignment between the project's output (user stories) and the customer's expectations. User stories are intended to be a collaborative tool that captures requirements from a user's perspective in clear, simple language. The complaint about jargon indicates this purpose has not been met. According to Agile principles, the most effective response to stakeholder feedback is direct engagement and collaboration. The project manager should facilitate a conversation with the customer to understand their concerns and work together to rewrite the stories. This ensures the final user stories accurately reflect the customer's needs and are understood by all stakeholders, directly addressing the root cause of the complaint.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition.

Section 2.8, Stakeholder Performance Domain, p. 67: This section emphasizes that "Effective stakeholder engagement requires a collaborative approach... Engagement is an ongoing activity that supports alignment among stakeholders and the project team." Engaging the customer directly is a primary example of this principle.

2. Project Management Institute. (2017). Agile Practice Guide.

Section 5.2.4, Understand and Act, p. 52: This section states, "In agile approaches, the team expects requirements to change... The team works closely with the business representative (e.g., product owner) to understand the new or changed requirement and to adjust the work." The customer's complaint is a form of feedback that requires understanding and action.

Appendix A3.1, User Stories, p. 101: This appendix highlights that a user story is a "reminder to have a conversation with the customer." When the story is unclear or fails to meet expectations, the necessary action is to have that conversation.

3. Lucassen, G., Dalpiaz, F., van der Werf, J. M. E., & Brinkkemper, S. (2016). The use and effectiveness of user stories in practice. 2016 IEEE 24th International Requirements Engineering Conference (RE), 205-214.

Section III-A, The Card, Conversation, Confirmation (3Cs), p. 207: This academic paper reinforces that the "Conversation" aspect of a user story is critical for clarifying details and ensuring a shared understanding between developers and stakeholders. The customer's complaint signals a breakdown in this conversation, which must be re-established. (DOI: 10.1109/RE.2016.29)

Question 24

A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on 20 December might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays. What should the project manager do about this risk?
Options
A: Update the risk register and take advantage of the opportunity.
B: Review the supplier's contract to understand the terms of sale.
C: Accept the risk and update the risk register.
D: Insist that the supplier deliver the goods on the agreed date.
Show Answer
Correct Answer:
Update the risk register and take advantage of the opportunity.
Explanation
The scenario presents a risk with two facets: a threat (schedule delay) and an opportunity (cost savings from a tax reduction). Effective risk management requires evaluating both negative and positive aspects of an uncertain event. By delaying the delivery into January, the project can leverage the new government tax policy, potentially creating significant cost savings that may outweigh the impact of the schedule delay. The most appropriate initial action is to update the risk register to reflect this opportunity and then develop a response strategy to exploit it, such as formally agreeing with the supplier on a new delivery date in early January.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Newtown Square, PA: Project Management Institute.

Section 2.8, Uncertainty Performance Domain: This section emphasizes that uncertainty has two dimensions: threat and opportunity. It states, "The project team can then choose the best response from a range of possible responses to address the risk... For opportunities, responses can include exploit, enhance, share, and accept." The chosen answer (A) aligns with the "exploit" strategy.

2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Sixth Edition. Newtown Square, PA: Project Management Institute.

Section 11.5.2.5, Strategies for Opportunities: The "Exploit" strategy is recommended for high-priority opportunities. It involves taking action to ensure that the opportunity is realized. In this scenario, coordinating a January delivery to get the tax break is a clear example of exploiting an opportunity.

Section 11.2.3.1, Risk Register: The risk register is the primary output of the Identify Risks process. It is a living document that should be updated as new risks (both threats and opportunities) are identified and as response plans are developed.

3. Hillson, D. (2002). Extending the risk process to manage opportunities. PMIยฎ Global Congress 2002โ€”North America, San Antonio, TX. Newtown Square, PA: Project Management Institute.

This foundational paper argues that opportunities should be managed proactively with the same rigor as threats. It states that a mature risk management approach includes processes to "identify, assess, and manage opportunities." The scenario requires the project manager to move beyond a threat-centric view and actively manage the upside potential.

Question 25

During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team. What should the project manager do next?
Options
A: Incorporate the changes in the last sprint before the first release.
B: Call for an internal meeting to discuss the changes and their value.
C: Ask the product owner to prioritize the backlog with the project team.
D: Request the scrum team to prioritize the product backlog.
Show Answer
Correct Answer:
Ask the product owner to prioritize the backlog with the project team.
Explanation
The recurring issue of the product owner introducing mandatory features mid-sprint is causing sprint failures and team frustration. This indicates a breakdown in the Agile process. The project manager, acting as a facilitator or coach, should guide the team and product owner back to core Agile principles. The most appropriate action is to facilitate a collaborative session where the product owner and the project team prioritize the product backlog together. This reinforces the correct process: new work is added to the backlog, not injected into an active sprint. This collaborative prioritization ensures that the team understands the value of the features and can provide input on effort, leading to a more stable and predictable workflow and addressing the root cause of the frustration.
References

1. Agile Practice Guide. (2017). Project Management Institute.

Section 5.2.4, Product Backlog: "The product owner is responsible for the product backlog... The product owner collaborates with the team and other stakeholders to gather and define the items in the product backlog." This supports the collaborative nature of backlog management proposed in option C.

Section 4.2.5, Iteration Planning: This section explains that the team selects work from a prioritized backlog at the start of an iteration. Introducing mandatory work mid-iteration violates this principle.

2. A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. (2021). Project Management Institute.

Section 2.4, Planning Performance Domain: In adaptive environments, "planning is an ongoing activity... The product owner maintains the backlog of work to be done." This highlights the PO's role and the backlog as the central planning artifact.

Section 4.6.3, The Product Owner: "The product owner is responsible for maximizing the value of the product... This is done through the management and prioritization of the product backlog." This confirms that prioritization is the PO's accountability, making option D incorrect.

3. Schwaber, K., & Sutherland, J. (2020). The Scrum Guide. Scrum.org.

Product Owner section: "The Product Owner is also accountable for effective Product Backlog management, which includes... Ordering Product Backlog items." This reinforces that the PO owns prioritization.

Sprint section: "No changes are made that would endanger the Sprint Goal... The Sprint Backlog is a plan by and for the Developers." Adding a mandatory feature mid-sprint jeopardizes the Sprint Goal and bypasses the established planning process.

Question 26

A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module. The marketing department believes that a main competitor is working on a similar product. Which delivery approach should the project manager use for this project?
Options
A: Traditional delivery, to ensure high quality and that the product meets market demands
B: Extreme Programming (XP) delivery, to mitigate the high risk related to a new product
C: Iterative delivery, to ensure that user feedback is incorporated into the second iteration
D: Incremental delivery, to ensure that mobile capability is released fast to the users
Show Answer
Correct Answer:
Incremental delivery, to ensure that mobile capability is released fast to the users
Explanation
The primary driver in this scenario is the competitive pressure, which creates an urgent need to release the new mobile functionality to the market quickly. An incremental delivery approach is specifically designed for this purpose. This approach focuses on delivering a complete and usable subset of the product's functionality (an increment) to users as early as possible. By releasing the mobile module as the first increment, the organization can secure a market position and gain a competitive advantage before its rival can launch a similar product. This strategy prioritizes speed to market for a valuable feature set.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Project Management Institute.

Section 2.5.3, Development Approaches and Life Cycles, p. 32: The guide states, "An incremental approach is an adaptive development approach in which the deliverable is produced through a series of iterations that successively add functionality within a predetermined time frame. The deliverable contains a necessary and sufficient set of features to be considered complete only after the final iteration." This directly supports delivering the mobile module as a distinct, valuable piece of functionality quickly.

2. Project Management Institute & Agile Alliance. (2017). Agile Practice Guide. Project Management Institute.

Section 3.1, Life Cycle Selection, p. 19-20: Figure 3-1 illustrates the characteristics of different life cycles. It defines an incremental life cycle by its "Frequent, smaller deliveries." This aligns with the need to release the mobile capability fast to the users to counter a competitor.

3. Shenhar, A. J., & Dvir, D. (2007). Reinventing Project Management: The Diamond Approach to Successful Growth and Innovation. Harvard Business School Press.

Chapter 4, Adapting Project Management to the Project's Level of Novelty, Market, and Technology: The authors discuss how projects with high market uncertainty and a need to be first-to-market benefit from adaptive and incremental approaches that allow for rapid delivery of value to test the market and establish a foothold.

Question 27

A project manager for a technologically complex engagement reviews the key project indicators with the main stakeholders on a regular basis. During one of the meetings, the project sponsor explains that they are using the project manager's risk register as a way to communicate about the project at the executive level. How should the project manager ensure that project risks are reported accurately in the risk register?
Options
A: Review the risks throughout project execution.
B: Plan to update the risks at project closure.
C: Update the risks in the risk management plan.
D: List the project risks identified in the kick-off meeting.
Show Answer
Correct Answer:
Review the risks throughout project execution.
Explanation
The risk register is a living document that must be maintained throughout the project lifecycle to be effective. The Monitor Risks process is performed during project execution to track identified risks, identify new ones, and evaluate the effectiveness of risk responses. Since the project sponsor is using the risk register for executive-level communication, ensuring its accuracy through continuous review is critical for transparent and effective stakeholder management. This ongoing review ensures that the information presented is current, relevant, and provides a true picture of the project's risk exposure.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Project Management Institute, Inc.

Page 65, Section 2.6, Risk Performance Domain: "Risk is addressed continually throughout the project. The project team seeks to identify, assess, and address risks proactively throughout the project." This supports the principle of continuous review.

2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Sixth Edition. Project Management Institute, Inc.

Section 11.7, Monitor Risks: "Monitor Risks is the process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project." This directly describes the activity in option A.

Section 11.7.3.1, Project Documents Updates - Risk Register: "The risk register is updated as a result of the Monitor Risks process. The risk register updates may include... outcomes of risk reassessments, risk audits, and periodic risk reviews."

3. Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). Wiley.

Chapter 18, Section 18.10, Risk Monitoring, Tracking, and Control: This section emphasizes that "Risk monitoring, tracking, and control is a continuous process that is performed throughout the life of the project." This aligns with the need for ongoing review during execution.

Question 28

A company is implementing a project with team members located in different countries and time zones. Individual performance is satisfactory, but the team's performance as a whole is low, especially in terms of group activities. What should the project manager do?
Options
A: Negotiate for new team members.
B: Review and update the communications management plan.
C: Review and reassign team assignments.
D: Facilitate communication and team building.
Show Answer
Correct Answer:
Facilitate communication and team building.
Explanation
The core issue described is a lack of team synergy and cohesion, not individual incompetence. In a geographically dispersed team, low performance in group activities despite satisfactory individual work points directly to challenges in communication, collaboration, and trust. The project manager's role as a leader and facilitator is crucial in this context. Actively facilitating communication and implementing team-building activities are direct interventions to foster a collaborative environment, build interpersonal relationships, and improve the team's ability to work together effectively. This approach addresses the root cause of the problem rather than just its symptoms.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Project Management Institute.

Section 2.2, Team Performance Domain: This domain emphasizes that "projects are performed by people," and a key activity is developing the team. It states, "Project teams that work collaboratively can accomplish a shared objective more effectively and efficiently than individuals working on their own." (p. 40). Facilitating communication and team building are core to fostering this collaborative environment.

2. Project Management Institute. (2017). Agile Practice Guide. Project Management Institute.

Section 5.2.2, Servant Leadership Responsibilities: This section highlights the project manager's role in "Building a collaborative team environment where the team can be effective" and "Facilitating" team interactions. These actions are essential for overcoming the challenges of distributed teams. (p. 35).

3. Hertel, G., Geister, S., & Konradt, U. (2005). Managing virtual teams: A review of current empirical research. Human Resource Management Review, 15(1), 69-95.

This academic review synthesizes research on virtual teams, concluding that success is highly dependent on socio-emotional processes. It highlights the importance of "interventions aimed at fostering team cohesion and trust (e.g., team-building)" and structured communication to overcome the lack of informal, face-to-face interaction. (pp. 79-81). https://doi.org/10.1016/j.hrmr.2005.01.002

Question 29

A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV) to actual cost (AC) for the project and has found the calculated result to be 0.9024. What does this value mean for the project?
Options
A: The project has started exceeding the planned cost.
B: The project is earning less value an was planned.
C: The project has earned more value than planned.
D: The project is close to exceeding the planned cost.
Show Answer
Correct Answer:
The project has started exceeding the planned cost.
Explanation
The ratio of Earned Value (EV) to Actual Cost (AC) is the Cost Performance Index (CPI). The formula is CPI = EV / AC. A CPI value less than 1.0 indicates a cost overrun, meaning the project is spending more than planned for the work that has been completed. With a CPI of 0.9024, for every dollar of cost incurred, the project is only earning approximately 90 cents of the value it was planned to earn. This signifies an unfavorable cost variance and confirms that the project is exceeding its planned cost for the work performed to date.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Project Management Institute, Inc. Section 2.7.3, Performance Measurement, p. 81. (This section discusses the use of EVM metrics like CPI to measure project performance against the baseline).

2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Sixth Edition. Project Management Institute, Inc. Section 7.4.2.2, Data Analysis, pp. 261-263. (This section explicitly defines CPI = EV/AC and states, "A CPI value less than 1.0 indicates a cost overrun for the work completed.").

3. Fleming, Q. W., & Koppelman, J. M. (2016). Earned Value Project Management (4th ed.). Project Management Institute. Chapter 4, "The Performance Indexes," p. 31. (This PMI-published standard explains that a CPI value below 1.0 indicates the project is getting less than one dollar's worth of work for each dollar spent).

4. Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). Wiley. Chapter 13, "Cost Control," Section 13.11. (This academic textbook details EVM, defining CPI and explaining that a value less than 1 signifies a cost overrun).

Question 30

A company is implementing a growth strategy by constructing a new production facility, which will soon move into the operation phase. Although a governance policy was already in place, the company must comply with new financial regulations that have been recently implemented. Compliance with the regulations will cause a major change in project scope. How should the project manager respond to this requirement?
Options
A: Proceed with the existing company governance policy.
B: Perform an analysis to assess the impact on the project.
C: Directly comply with the financial regulations.
D: Escalate the issue to upper management and let them decide.
Show Answer
Correct Answer:
Perform an analysis to assess the impact on the project.
Explanation
When a project is confronted with a mandatory change, such as new regulatory compliance, the project manager's immediate responsibility is to follow a formal change control process. The first and most critical step in this process is to conduct a thorough impact analysis. This analysis evaluates the effects of the proposed change on all project constraints, including scope, schedule, budget, quality, resources, and risk. This data-driven assessment is essential for stakeholders and the change control board to make an informed decision about how to incorporate the change. Acting without this analysis would be a breach of professional project management practice.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Project Management Institute, Inc. See Section 2.8, "Project Work Performance Domain," which discusses the need for a process to manage project changes. It states, "A change control process can include (but is not limited to):...Evaluate the impact to the project..." (p. 107).

2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Sixth Edition. Project Management Institute, Inc. The "Perform Integrated Change Control" process (Section 4.6) explicitly requires the assessment of impacts as a core activity. The process description emphasizes that "each change request has to be assessed for its impact on all project constraints" (p. 113).

3. Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). John Wiley & Sons. In Chapter 14, "Project Control," the text outlines the configuration and change control process, highlighting that a critical step after a change is identified is the "evaluation of the change" to determine its impact on the project baselines before any approval or implementation.

Question 31

A project is implementing an agile strategy, and a minimum viable product (MVP) was agreed upon. After the first iteration review, the customer explained that the first deliverable is not of great value. What should the project manager have done differently?
Options
A: Invited the customer to the daily meetings
B: Helped the team redefine the MVP
C: Changed the duration of iterations to deliver more value
D: Validated the iteration goals with the customer
Show Answer
Correct Answer:
Validated the iteration goals with the customer
Explanation
The fundamental issue is a misalignment between the development team's work and the customer's expectation of value for a specific iteration. In agile approaches, each iteration should deliver a valuable increment of the product. The iteration goal, established during iteration planning, serves as a guiding objective for the team. By validating this goal with the customer before the iteration begins, the project manager ensures that the team's efforts are focused on what the customer considers most important at that moment. This proactive alignment is a key practice to prevent delivering features or functions that do not meet the customer's immediate needs or value perception.
References

1. Agile Practice Guide, Project Management Institute. (2017). Section 5.2.5, Iteration Planning, p. 54. This section explains that the team and the product owner establish the goal for the iteration. The product owner represents the customer's interests, and ensuring alignment on this goal is critical for delivering value. The guide states, "The team and the product owner establish the goal for the iteration."

2. A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition, Project Management Institute. (2021). Section 2.2, Stakeholder Performance Domain, p. 31. This domain emphasizes that "Effective stakeholder engagement includes implementing strategies and actions to promote productive involvement of stakeholders." Validating iteration goals is a key action for engaging the customer to ensure alignment on value.

3. Schwaber, K., & Sutherland, J. (2020). The Scrum Guide. Scrum.org. p. 9. The official Scrum Guide, heavily referenced by PMI, states, "The Sprint Goal is the single objective for the Sprint... The Product Owner proposes how the product could increase its value and utility in the current Sprint." This highlights the importance of aligning the iteration's objective with stakeholder-defined value.

Question 32

A project team has expressed concern that certain remote team members are not able to collaborate with the larger project team due to their work schedule. The project manager is confused since the entire team is located in the same time zone and believes there are other factors at play. What should the project manager do next?
Options
A: Rectify ground rule violations.
B: Review performance formally.
C: Examine the team's virtual needs.
D: Implement new options.
Show Answer
Correct Answer:
Examine the team's virtual needs.
Explanation
The project manager suspects the stated reason for the collaboration issue (work schedule) is not the root cause. The most effective next step is to investigate the underlying factors. Since the issue involves remote team members, a focused examination of their virtual needs is the most logical diagnostic action. This involves assessing the adequacy of communication tools, collaboration platforms, team norms for virtual interaction, and potential feelings of isolation. This approach aligns with the project manager's role as a facilitator who must first understand a problem before attempting to solve it.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition.

Section 2.2, Team Performance Domain: This domain emphasizes creating an environment that fosters team development and collaboration. It states, "For virtual teams, the project manager can foster a sense of community by ensuring there are opportunities for the team to get to know each other, and by using multiple communication technologies..." (p. 48). This supports the need to first examine the specific needs related to the virtual environment.

2. Project Management Institute. (2017). Agile Practice Guide.

Section 5.2.2, Servant Leadership: This section describes the role of a servant leader in "understanding and addressing team member and stakeholder needs" (p. 34). Before taking any action, the project manager should first seek to understand the team's needs, which in this case are their virtual needs.

3. Hertel, G., Geister, S., & Konradt, U. (2005). Managing virtual teams: A review of current empirical research. Human Resource Management Review, 15(1), 69-95.

Abstract & Section 3: The paper highlights that effective management of virtual teams requires addressing specific challenges related to communication, coordination, and social cohesion. This underscores the importance of examining the team's virtual needs (e.g., technology support, communication protocols) as a primary step in resolving collaboration issues. (DOI: https://doi.org/10.1016/j.hrmr.2005.01.002)

Question 33

A project manager recently finished a project and started managing a new project with a different supervisor. As part of the early project activities, the supervisor from the original project is assigned to the team as a nonsupervisory resource and immediately begins challenging all decisions made by the current supervisor. What should the project manager do to resolve this conflict?
Options
A: Give the project team time to work through the issues with the new supervisor.
B: Ensure the new supervisor takes the lead when being challenged.
C: Immediately remove the resource from the project team.
D: Communicate with the resource on the roles and responsibilities of this project.
Show Answer
Correct Answer:
Communicate with the resource on the roles and responsibilities of this project.
Explanation
The root cause of the conflict is the former supervisor's apparent difficulty in adjusting to their new, non-supervisory role. The most effective and professional first step is for the project manager to address this issue directly through clear communication. By discussing and reinforcing the established roles and responsibilities for the current project, the project manager can clarify expectations and resolve the misunderstanding that is fueling the conflict. This approach aligns with the conflict resolution technique of confronting/problem-solving, which seeks a direct resolution by focusing on the underlying issue.
References

1. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) (6th ed.). Section 9.4.2.2, Conflict Management. This section describes "Collaborate/problem solve" as a key technique, which involves "examining different viewpoints... to reach consensus and commitment." Communicating roles and responsibilities (Option D) is a direct application of this problem-solving approach.

2. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) (7th ed.). Section 2.4, Team Performance Domain. This domain emphasizes the project manager's role in fostering a collaborative environment and managing conflict. It states, "Conflict is inevitable on projects. It can be constructive if it is managed well... Proactively addressing conflict with a willingness to have difficult conversations can help teams."

3. Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). John Wiley & Sons. In Chapter 5, "Conflicts," Kerzner discusses that conflicts over project priorities, administration, and roles are common. The recommended approach is confrontation (problem-solving), which involves directly addressing the conflict's source, in this case, the role ambiguity.

4. Tjosvold, D. (2008). The conflict-positive organization: It depends upon us. Journal of Organizational Behavior, 29(1), 19-28. This article supports the idea that proactively confronting and discussing conflicts over roles and authority leads to more constructive outcomes and strengthens team relationships, rather than avoiding the issue. (https://doi.org/10.1002/job.473)

Question 34

product development team has team members located in four different countries. A senior manager is assigned the task of recruiting a project manager to manage this project and the virtual team. Which skill is required for a project manager to successfully manage this team?
Options
A: Speaks several languages and has lived in different countries
B: Possesses strong interpersonal skills to drive high-performing virtual teams
C: Plans and controls every aspect of the team's deliverables to avoid surprises
D: Implements the organizationโ€™s standards and processes for the project
Show Answer
Correct Answer:
Possesses strong interpersonal skills to drive high-performing virtual teams
Explanation
Managing a geographically dispersed, virtual team requires a project manager to overcome challenges related to communication, cultural differences, and team cohesion. Strong interpersonal skillsโ€”often referred to as "power skills" by PMIโ€”are essential for building trust, fostering a collaborative environment, and motivating team members who lack face-to-face interaction. These skills, which include communication, emotional intelligence, and conflict resolution, are the foundation for creating and leading a high-performing virtual team, enabling the project manager to bridge geographical and cultural divides effectively.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition. Project Management Institute, Inc.

Section 2.3, Team Performance Domain, p. 43: This section emphasizes that creating a safe, trusting, and collaborative environment is a key element for a high-performing team. The activities to achieve this, such as building a culture of respect and managing conflict, are all rooted in strong interpersonal skills.

Section 2.3.3, Project Team Culture, p. 47: It is noted that "For virtual teams, it is important to foster the team environment intentionally," which directly points to the project manager's active role in using interpersonal skills to build team culture.

2. Project Management Institute. (2021). The Standard for Project Management. Project Management Institute, Inc.

Section 3.2, Create a collaborative project team environment, p. 29: This principle states that project teams work most effectively in a collaborative environment. The project manager is responsible for fostering this environment, which relies heavily on interpersonal abilities like communication and relationship-building.

3. Hertel, G., Geister, S., & Konradt, U. (2005). Managing virtual teams: A review of current empirical research. Human Resource Management Review, 15(1), 69-95.

p. 81: The review highlights the critical role of leadership in facilitating "socio-emotional processes" such as building trust and providing social support, which are essential for virtual team effectiveness and are components of interpersonal skill. (https://doi.org/10.1016/j.hrmr.2005.01.002)

Question 35

A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not be able to provide assistance for 1 week. How should the project manager address this situation?
Options
A: Ask the team member to find an innovative solution or workaround to overcome the issue and avoid project delays.
B: Schedule a meeting with the project sponsor to request a budget to buy or rent a new computer.
C: Explore options with the IT department to expedite the necessary repairs based on criticality of the project.
D: Use project reserves to buy new equipment to avoid an impact to the critical path of the project.
Show Answer
Correct Answer:
Explore options with the IT department to expedite the necessary repairs based on criticality of the project.
Explanation
The project manager's primary responsibility is to facilitate project progress by removing impediments for the team. The IT department's initial response is based on their standard workload and queue, which may not account for the specific, critical nature of this project's deliverable. The most appropriate first step is for the project manager to engage in collaborative problem-solving with the IT department. By communicating the project's criticality and the potential impact of the delay, the project manager can negotiate to have the repair expedited. This approach addresses the root cause directly and leverages organizational relationships before escalating or using contingency funds.
References

1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKยฎ Guide) โ€“ Seventh Edition.

Section 2.2, Team Performance Domain, p. 49: This section highlights servant leadership, which includes "removing impediments, obstacles, and blockers for the team." The situation described is a classic blocker that the project manager is responsible for addressing.

Section 2.8, Project Work Performance Domain, p. 103: This domain involves managing physical resources and "ensuring that team members have the resources they need." When a resource becomes unavailable, the project manager must take action to resolve the issue.

2. Project Management Institute. (2017). Agile Practice Guide.

Section 5.2.2, Servant Leadership, p. 34: This section explicitly lists "Addressing and removing impediments" as a key practice for project leaders. The guide emphasizes that servant leaders "remove impediments that are blocking the team's progress."

3. Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). Wiley.

Chapter 5, Management Functions, Section 5.10, Controlling, pp. 204-205: This university-level textbook explains that a key project management function is taking corrective action. This includes negotiating with functional managers (like the head of IT) to resolve resource conflicts and ensure project priorities are met.

Shopping Cart
Scroll to Top

FLASH OFFER

Days
Hours
Minutes
Seconds

avail $6 DISCOUNT on YOUR PURCHASE